Vietnam.vn - Nền tảng quảng bá Việt Nam

Sprint to disburse public investment capital

Việt NamViệt Nam21/01/2025


According to regulations, the 2024 public investment capital plan will be implemented until the end of January 2025. With a high determination, Yen Lap district is making efforts to focus on directing and urging investors and contractors to speed up the construction progress of works and projects, while removing related difficulties and obstacles, in order to complete the proposed investment capital disbursement plan.

Yen Lap: Sprint to disburse public investment capital

The project to renovate and upgrade the inter-commune road from Luong Dau area, Dong Thinh commune to Xen area, Phuc Khanh commune is being focused on accelerating the progress, striving to complete and put into use before the Lunar New Year of At Ty 2025, finishing 3 months ahead of the signed construction contract.

Bustling on construction sites

Starting in early October 2024, the project to build a new 2-storey classroom building, 8 classrooms and expand the campus of Xuan Vien kindergarten (Yen Lap district) with a total investment of 8.5 billion VND is being accelerated by the joint venture of Lan Phuong Linh Trading Joint Stock Company - Max Vietnam Electromechanical Company Limited with human resources and machinery.

Mr. Ha Ngoc Anh - Director of Lan Phuong Linh Company said: "Immediately after receiving the project site, we mobilized human resources and equipment to focus on constructing the project items. Up to now, the unit has completed about 35-40% of the work volume, including completing the foundation, building the first floor walls and is constructing the formwork and reinforcing steel for the first floor roof. Taking advantage of favorable weather, we strive to complete the concrete pouring of the entire first floor roof before the Lunar New Year holiday and deploy each project item according to plan, committed to ensuring the construction progress of the items to hand over the project on the occasion of the 135th anniversary of President Ho Chi Minh's birthday (May 19, 2025) as committed to the investor".

In the lower part of Yen Lap district, in the early days of January, the construction site for the renovation and upgrading of the inter-commune road from Luong Dau area, Dong Thinh commune to Xen area, Phuc Khanh commune is always bustling and busy. Dozens of workers along with many vehicles and machines are working overtime, focusing on the final items of the project such as pouring concrete on the road surface, reinforcing drainage ditches, installing signs and road signs to ensure traffic safety... Both the investor, contractor, and workers are determined to speed up the progress, complete and put the project into use before the Lunar New Year of At Ty 2025, finishing 3 months ahead of the original schedule and the signed construction contract.

“To ensure the construction project is implemented on schedule, we have directed the contractor to take advantage of favorable weather conditions and mobilize workers to work 3 shifts per day. With the spirit of working urgently regardless of rain or shine, up to now, the project items have been basically completed, serving the travel needs of the people, while simultaneously connecting synchronously with the existing traffic infrastructure system in the area; thereby enhancing the ability to transport goods, promoting the socio-economic development of the locality” - Mr. Nguyen Xuan Thuy - project manager of the Yen Lap District Investment and Construction Project Management Board said.

Yen Lap: Sprint to disburse public investment capital

Construction of roadbed for the project to renovate and upgrade the road from Rung Cao area to Xuan Ha area, My Lung commune, Yen Lap district.

Determined to achieve the best results

Comrade Ha Viet Hung - Deputy Secretary of the District Party Committee, Chairman of the People's Committee of Yen Lap district said: In 2024, Yen Lap district was assigned a total adjusted public investment capital of more than 292.5 billion VND from the central budget, provincial budget and local budget. The capital sources were allocated for 76 finalized projects, 9 completed projects and expected to be completed in the year, 106 transitional projects, and 51 newly started projects. To ensure the disbursement of public investment capital according to plan, most of the projects in the district were mobilized by contractors to the maximum extent of machinery, equipment and human resources to speed up construction progress.

The District Construction Investment Project Management Board, the People's Committees of communes and towns in the area and the district's functional agencies regularly inspect the site to promptly handle problems during the construction process, adjust the progress, and avoid delays compared to the contract. At the same time, coordinate with the construction unit in the acceptance of completed volume, prepare payment documents to disburse capital when payment conditions are met.

With many solutions to overcome difficulties in investment preparation and construction organization, by December 31, 2024, Yen Lap district had disbursed more than 92% of public investment capital compared to the plan. Mr. Bui Xuan Tien - Director of Yen Lap District Construction Investment Project Management Board, said: The process of basic construction investment in 2024 encountered many difficulties. Specifically, 2024 is the first year of applying the revised Land Law and Bidding Law, thus greatly affecting the documents and legal procedures for project implementation. Investment preparation for projects encountered difficulties, prolonged procedures related to planning approval and environmental impact assessment. New investment projects and key projects still have problems with compensation and resettlement support; The capacity and construction methods of some contractors are not guaranteed... In addition to the projects invested by the District Construction Investment Project Management Board, the agencies, units, People's Committees of communes and towns assigned to implement projects, sub-projects, joint lead units, and community production development teams are still implementing them in a confused manner.

The review work to ensure the correct subjects, regimes, policies and objectives of the project has affected the implementation and disbursement process of a number of projects and sub-projects... However, thanks to good leadership and direction, focusing on drastic and synchronous implementation of tasks and solutions to accelerate the construction progress, put the project into use and disburse public investment capital in 2024 right from the first days and months of 2024. In particular, urging investors to promptly and quickly complete disbursement procedures such as procedures for counting or accepting volume, or procedures for payment and settlement documents, so the disbursement progress of Yen Lap's public investment capital is currently being implemented very drastically.

There is less than half a month left to implement the 2024 public investment plan. Time clearly does not wait for us. Accelerating the disbursement of public investment capital at this time is the imperative of economic growth and requires high concentration on implementing flexible, creative, timely and effective measures and solutions.

Faced with the requirements for the task of disbursing public investment capital, the People's Committee of Yen Lap district is focusing on directing and urging specialized departments and offices to continue to improve their responsibility in investment management. At the same time, continuously inspect and promptly detect difficulties and obstacles to make recommendations to competent authorities and have timely solutions.

The district has also issued documents, directing heads of agencies and units; Chairmen of People's Committees of communes and towns; investors and project owners to identify accelerating the progress of implementation and disbursement of capital as the top important political task, the direct task of heads of Party committees, authorities, and relevant agencies and units. The Finance - Planning Department has directed specialized departments to focus on and urgently appraise contractor selection plans, appraise and approve the final settlement of completed projects, and appraise national target program projects by component.

Continue to coordinate with the Department of Finance to fully import capital sources on the TABMIS system. Yen Lap State Treasury focuses on implementing capital payments for works and projects that have met the conditions to ensure the prescribed time; closely coordinate with investors and project owners to handle arising problems, shortening the time for controlling expenditures. Construction units focus highly on human resources, vehicles, materials, taking advantage of favorable weather conditions and overcoming difficult weather conditions to speed up construction progress according to the allocated capital plan, with the highest determination to strive for the goal of disbursing 100% of public investment capital, National Target Programs planned for 2024 and previous years.

Dinh Vu



Source: https://baophutho.vn/yen-lap-chay-nuoc-rut-giai-ngan-von-dau-tu-cong-226851.htm

Comment (0)

No data
No data

Same tag

Same category

Phu Quoc - a vacation that awakens the senses
Why is the upcoming Vietnamese blockbuster 'Snow White' receiving a strong reaction from the audience?
Phu Quoc in top 10 most beautiful islands in Asia
People's Artist Thanh Lam is grateful to her doctor husband, and "corrects" herself thanks to marriage

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product