The project was approved by the City People's Committee in Decision No. 1933 dated July 25, 2022, with a total investment of over 148 billion VND, with a capacity of 7,000 people and auxiliary works, synchronous technical infrastructure system inside and outside the house.
Up to now, the project has basically completed the rough construction items; is constructing the structural covering items, finishing the project and technical infrastructure items outside the house. The cumulative completed construction volume is about 75 billion VND (60% of the volume, contract value). The cumulative capital provision is 114 billion VND (accounting for 77% of the total estimate). The cumulative disbursement for construction and installation is nearly 68 billion VND; payment for completed volume is 39 billion VND.
Source: http://baovinhphuc.com.vn/Multimedia/Images/Id/126637/Phan-dau-dua-du-an-San-van-dong-thanh-pho-Vinh-Yen-di-vao-hoat-dong-trong-thang-10