Vietnam.vn - Nền tảng quảng bá Việt Nam

Need to quickly remove site obstacles and speed up construction

Việt NamViệt Nam08/04/2025


3.jpg
Asphalt concrete layer 1 connecting the two communes of Tien Phong and Tien My (Tien Phuoc). Photo: CONG TU

Speed ​​up progress

At the Tien Phong - Tien My section (Tien Phuoc), 6.5/8.55km (76%) of the surface length has been handed over. The Quang Nam Provincial Traffic Construction Investment Project Management Board (investor) has directed the contractor Thang Long Corporation - JSC to test asphalt concrete last week. Engineer Nguyen Van Thuan, technical officer in charge of the Thang Long Corporation - JSC, shared that the contractor strives to complete the first layer of asphalt concrete with a total length of 2.5km connecting Tien Phong with Tien My this April.

5.jpg
Construction of drainage ditches along the section through Tai Da village (Tien Phong commune). Photo: CONG TU

The contractor continues to complete the cross-road culverts, longitudinal ditches, reinforced ditches, and road foundations to pave the second phase of asphalt by the end of May 2025. Director of the Project Management Board for Investment and Construction of Traffic Works in Quang Nam Province - Mr. Nguyen Van Thuong said that the section through Tien Canh - Tien Hiep is 13.32km long, the investor has just received the top of Lieu Pass on Tien Hiep side, about 250m, and on Tien Canh side, about 700m. The handed-over site is not continuous, with the electrical infrastructure and fiber optic cables not yet relocated. Therefore, the contractor mainly digs down the pass base and then coordinates the soil to fill the section through Phu Ninh district.

4.jpg
Construction of the upper part of Truong Giang bridge (Binh Nam commune, Thang Binh) is underway. Photo: CONG TU

The project through Phu Ninh district is 1.9km long. Up to now, the district has handed over 1.8km, the remaining area is the intersection with DT615 route. The contractor is currently constructing more than 33,600m3 of roadbed (total 63,000m3 ).

In Thang Binh district, the project is 2km long, including Truong Giang bridge. At the Truong Giang bridge construction site (Binh Nam commune), the contractor has completed the lower part; the upper part has been installed and poured concrete for 4/8 of the bridge's surface, and is installing the beam of the 5th span.

[VIDEO] - At the Truong Giang bridge construction site:

The project passes through Bac Tra My district, the investor has received 5.1/5.7km of handover. Mr. Nguyen Van Thuong said that the contractor has basically completed the horizontal culverts and longitudinal ditches, is making reinforced trenches, and reinforcing the slope on the received clean ground. The construction of the crushed stone foundation is 3.5km long. If the weather is favorable, the first phase will be paved with asphalt concrete for 3.5km in April 2025.

Need to remove land obstacles

8(1).jpg
Road access to Truong Giang bridge is blocked. Photo: CONG TU

According to the investor, Thang Binh has just handed over 0.7km of land; but only 0.34km is continuous for the girder casting yard and the Truong Giang river surface, the remaining 0.36km is discontinuous and has no access road for construction. In order to resettle the affected households, Nghia Hoa residential area needs to be built, but up to now, this residential area has not been built yet. Not to mention, Thang Binh still has 80 plots/56 households that have not submitted compensation and support plans to proceed to the next step.

The entire 600m of land length through Bac Tra My that has not been handed over belongs to the design adjustment section in front of Duong Yen Protestant Church and the two resettlement households, Ms. Tra Thi Tam and Mr. Doan Ngoc Tuan (Tra Duong commune). It is worth noting that both households of Ms. Tam and Mr. Tuan agreed on the compensation, support and resettlement plan before August 1, 2024. After that, the 2024 Land Law took effect, so we have to wait for the Provincial People's Committee to issue new relevant regulations.

The implementation of site clearance is stuck because the previous compensation and support value has decreased significantly compared to current regulations. Specifically, the coefficient of constructions and architectural works has decreased from 1.4 to 1.05. Accordingly, Mr. Tuan's household has decreased by about 240 million VND; Mrs. Tam's household has decreased by about 226 million VND. In addition, applying the transition according to the provisions of Decision No. 31 of the Provincial People's Committee on compensation, support and resettlement when the State recovers land in the province, Mrs. Tam's household is only supported with the difference in land use fees corresponding to 100m2 (1 resettlement land plot; not supported with 2 resettlement land plots according to the content discussed in Decision No. 42, dated December 21, 2021 of the Provincial People's Committee).

[VIDEO] - An unopened location in Tien My commune (Tien Phuoc) due to land issues of a household:

The total area of ​​the section through Tien Phuoc has only been handed over 7.2/21.48km. To date, there are still 76 plots of land without legal confirmation (30 plots in Tien Canh, 46 plots in Tien Hiep). The section through Tien Phong - Tien My has 47 households that have approved the compensation, support, and resettlement plans but have not yet agreed to receive money; similarly, Tien Canh commune has 102 households. Regarding the construction of resettlement areas, Dong Ba Hien (Tien Phong) and Dong Quan (Tien My) areas have selected construction contractors but have not yet started construction; Tien Canh, Tien Hiep, and Dong Chua (Tien My) resettlement areas have selected construction contractors.

The resettlement areas of the project are in the investment implementation phase. Therefore, the locality has not yet had a basis to establish a compensation, support, and resettlement plan for households affected by resettlement housing. In addition, the construction process until the affected households accept the resettlement plot and build houses takes a lot of time...



Source: https://baoquangnam.vn/du-an-lien-ket-vung-mien-trung-tinh-quang-nam-can-som-go-vuong-mat-bang-day-nhanh-thi-cong-3152295.html

Tag: traffic

Comment (0)

No data
No data

Same tag

Same category

Young people "revive" historical images
Watching the silver coral reefs of Vietnam
Close-up of the soldiers' hard training hours before the April 30th celebration
Ho Chi Minh City: Coffee shops decorated with flags and flowers to celebrate the 30/4 holiday

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product