400m of road under construction again after 14 years of being 'forgotten'

Báo Tiền PhongBáo Tiền Phong08/01/2025

TPO - After 14 years of being "forgotten" due to land and capital problems, a road section of more than 400m long through Ky Ninh commune, Ky Anh town (Ha Tinh) has been funded for completion.


TPO - After 14 years of being "forgotten" due to land and capital problems, a road section of more than 400m long through Ky Ninh commune, Ky Anh town (Ha Tinh) has been funded for completion.

Close-up of a 400m stretch of road that has been “forgotten” for 14 years. Video: Pham Truong.

400m of road under construction again after 14 years of being 'forgotten' photo 1

In the last days of the year, workers and machines are still constructing a road section of more than 400m long through Ky Ninh commune, Ky Anh town (Ha Tinh). This is a road section that has been “missing” for the past 14 years due to land and funding issues, so construction cannot be carried out.

400m of road under construction again after 14 years of being 'forgotten' photo 2
According to the Management Board of the Ha Tinh Economic Zone Construction Investment Project (investor), the above road section belongs to the Central Urban Area - Ky Ninh Tourist Urban Area Cross-Road Project (phase 1), approved by the Ha Tinh Provincial People's Committee in 2010 with a total investment of over 319 billion VND. The total length of the entire route is over 9.2km.
400m of road under construction again after 14 years of being 'forgotten' photo 3

In phase 1, the project completed 8.8/9.2 km of construction, meeting the standards of a grade III road. At that time, more than 400m through Tan Thang village, Ky Ninh commune could not be constructed due to land clearance problems. In the picture, the road section has been re-constructed after 14 years of being "forgotten".

400m of road under construction again after 14 years of being 'forgotten' photo 4

"The investor has asked the construction unit to take advantage of favorable weather to speed up the progress to complete the road for people to travel," said a representative of the Management Board of Investment and Construction Projects in the Ha Tinh Economic Zone.

400m of road under construction again after 14 years of being 'forgotten' photo 5

Some residents in the project area have relocated and handed over the site for road construction. “The road has not been constructed for the past 14 years, making it difficult and dangerous for people to travel. I hope the contractor will soon complete the road,” said a resident of Ky Ninh commune.

400m of road under construction again after 14 years of being 'forgotten' photo 6

Bac A Construction and Trading Joint Stock Company was assigned to construct the road. Currently, the project implementation unit has completed the drainage ditch, excavation and filling of the ground, and transported the components to the work site.

400m of road under construction again after 14 years of being 'forgotten' photo 7400m of road under construction again after 14 years of being 'forgotten' photo 8400m of road under construction again after 14 years of being 'forgotten' photo 9

Mr. Nguyen Van Thai, Director of Bac A Construction and Trading Joint Stock Company, said that the construction unit has been working for nearly a month, but due to heavy rain, the workload is not large. "This route has a lot of traffic, the weather is not favorable, so the construction is very difficult. The unit will try to complete the road surface before Tet, spread crushed stone for people to travel and complete more", Mr. Thai informed.

400m of road under construction again after 14 years of being 'forgotten' photo 10

The constant traffic volume causes the road to form large potato beds, making construction difficult.

400m of road under construction again after 14 years of being 'forgotten' photo 11

The road is being cleared and a drainage system is being constructed. Local leaders said that people are very happy that the road has been re-invested and hope that the road will be completed before Tet to facilitate trade and celebrate Tet.

350m of road that has not been constructed after 14 years
350m of road that has not been constructed after 14 years

Waiting wearily for the 14-year-old 'suspended' road expansion project in Hanoi
Waiting wearily for the 14-year-old 'suspended' road expansion project in Hanoi

People had to climb ladders up the rusty bridge because there was no access road.
Bridges and roads under construction for 14 years are still unfinished

Pham Truong



Source: https://tienphong.vn/400m-duong-thi-cong-tro-lai-sau-14-nam-bi-bo-quen-post1707777.tpo

Comment (0)

No data
No data

Same tag

Same category

Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product