Vietnam.vn - Nền tảng quảng bá Việt Nam

1,100 billion VND National Highway in disarray before storm season

Báo Tiền PhongBáo Tiền Phong11/09/2024


Ha Tinh:

TPO - After nearly 1 year of construction, the project to renovate and upgrade National Highway 8C from Thien Cam - National Highway 1 through Ha Tinh province is still in disarray before the storm season due to the land not being handed over yet.

Close-up of the National Highway 8C project, which has been upgraded with an investment of nearly 1,100 billion VND. Video: Pham Truong.

National highway worth 1,100 billion VND in disarray before the storm season photo 1

The project to upgrade and expand National Highway 8C from Thien Cam town to National Highway 1 (Cam Xuyen district) and the intersection of National Highway 8A in Son Long commune to the intersection of Ho Chi Minh road (Son Trung commune, Huong Son district) has a total length of 27.7km. The project is invested by the Ha Tinh Department of Transport with a capital of nearly 1,100 billion VND.

National Highway 1,100 billion VND in disarray before storm season photo 2

Deployed since October 2023, after nearly 1 year of construction, the project is still in disarray due to land acquisition problems. In addition, the route is also entangled with medium and low voltage power lines; clean water pipeline system, making construction of the units extremely difficult.

National highway worth 1,100 billion VND in disarray before storm season photo 3

Mr. Luong Tien Thanh - an officer of the Ha Tinh Traffic Construction Investment Project Management Board said that the contractors have basically completed the production of precast components (longitudinal drainage ditches, horizontal culverts); filled the soil; installed longitudinal ditches, horizontal culverts and basically constructed the Dun and Gon bridges...

National highway worth 1,100 billion VND in disarray before storm season photo 4

"The project has only reached more than 30% because there are still 160/900 households with unfinished land. The unit is coordinating with the locality to soon hand over the land to the construction units according to the set schedule," said Mr. Thanh.

National highway worth 1,100 billion VND in disarray before storm season photo 5National highway worth 1,100 billion VND in disarray before storm season photo 6National Highway 1,100 billion VND in disarray before storm season photo 7

The site is still stuck, forcing the contractor to jump around in construction. The soil system is weathered and the drainage ditches are lying in disarray.

National Highway 1,100 billion VND in disarray before storm season photo 8

At this time, at the construction site, the contractor has arranged many construction equipment and machinery to complete the roadbed embankment at the road expansion locations before the rainy season.

National Highway 1,100 billion VND in disarray before storm season photo 9

According to the contractors, because the land has not been handed over yet, construction cannot be carried out at the same time, but instead, machinery and workers will be deployed wherever land is available. In the picture, the "hopping" construction also causes difficulties for people traveling on the route.

National Highway 1,100 billion VND in disarray before storm season photo 10National Highway 1,100 billion VND in disarray before storm season photo 11

The structure lies scattered with weathered soil and dust.

National Highway 1,100 billion VND in disarray before storm season photo 12

The investor representative said that the amount of fill soil for the project is very scarce. The estimated soil mines near the project site are mostly filled with rocks, forcing the construction units to be proactive and accept to take fill soil from further locations.

National Highway 1,100 billion VND in disarray before storm season photo 13National Highway 1,100 billion VND in disarray before storm season photo 14National Highway 1,100 billion VND in disarray before storm season photo 15

The investor is urging contractors to complete construction at locations with available land to meet the set schedule before the flood season. Meanwhile, the People's Committee of Cam Xuyen district said it has completed 100% of the inventory of households affected by the project. The locality is focusing on determining the origin and time of land use and property use to have a basis for pricing, approving and paying appropriate compensation costs, and soon having a clean land for the project.

Pham Truong



Source: https://tienphong.vn/quoc-lo-1100-ty-dong-ngon-ngang-truoc-mua-mua-bao-post1671583.tpo

Comment (0)

No data
No data

Same tag

Same category

Southeast Asian fans react when Vietnam team defeats Cambodia
The sacred circle of life
Tombs in Hue
Discover the picturesque Mui Treo in Quang Tri

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product