Nhon metro tunnel boring machine

Báo Giao thôngBáo Giao thông07/03/2025

The tunnel boring machine (TBM) named Than Toc has arrived at S10 - Cat Linh station, marking an important milestone of the Hanoi urban railway pilot project, Nhon - Hanoi station section.


According to the Urban Railway Management Board, today (March 7), the No. 1 tunnel boring machine TBM named Than Toc has officially arrived at S10 - Cat Linh station, marking an important milestone in the construction of the Nhon - Hanoi station urban railway line.

Máy khoan hầm tuyến metro Nhổn - ga Hà Nội đã đến ga Cát Linh- Ảnh 1.

Contractors are excited because the tunnel boring machine has reached Cat Linh station.

The Speedy TBM is the first tunnel boring machine to be started in the CP03 package - Tunnels and underground stations of the project. Starting from S9 - Kim Ma station on July 30, 2024, after many months of safe operation, the machine has completed the drilling and installation of the tunnel lining with a length of more than 1,338m to reach S10 - Cat Linh station, strictly complying with technical and environmental standards.

TBM No. 2 started working from S9 station (Kim Ma station) on February 3. Both TBMs are expected to complete the entire tunnel boring work by the end of 2025.

After finishing drilling at station S12 - Hanoi station, the drilling heads of the TBMs will be dismantled at this station, the auxiliary equipment system will be pulled back and dismantled at station S9 - Kim Ma.

Mr. Nguyen Ba Son - Deputy Head of Hanoi Railway Management Board said: "The official arrival of TBM Than Toc at S10 - Cat Linh station is an important step forward for the project. This is the result of continuous efforts to overcome difficulties, as well as close coordination between Hanoi Urban Railway Management Board, Consultants, contractors and relevant parties in ensuring the progress, quality and safety of the project".

As of March 2, the overall construction progress of CP03 - Tunnel and underground stations package reached 55.38%. The underground ramp was 76.63% completed, S9 station was 50.50% completed, the vertical shaft was 24.51% completed, the tunnel line was 51.48% completed, and stations S10, S11, S12 (including lane change and garage) were 64.64%, 58.1%, 59.74% completed, respectively.

Construction activities are taking place at all construction sites. Specifically, station S10 - Cat Linh is deploying the southern auxiliary structure, mobilizing and installing the push frame system to receive the TBM; station S11 - Van Mieu Station has completed pouring concrete for the bottom slab; station 12 - Hanoi Station is constructing the transfer slab and excavating the ground for the mezzanine slab in parallel.

The Hanoi Urban Railway Management Board pledges to continue to closely coordinate with relevant parties to complete the next items, aiming to put the entire project into operation as soon as possible.

During the construction process, the Project will use a geotechnical monitoring system to ensure the monitoring and tracking of ground movement and subsidence. Tunnel boring will be carried out with caution and strict supervision to ensure the safety of existing structures as well as the quality of the construction under construction.

It is expected that the underground section will be completed in 2027, after which the entire urban railway line No. 3, Nhon - Hanoi station section will be put into operation, contributing to changing the face of the capital, conveniently connecting areas and promoting sustainable development, greening urban transport.

The Nhon - Hanoi Railway Station urban railway project is one of the city's key transport projects, contributing to reducing traffic congestion, improving the public transport system and enhancing the quality of the urban environment. The tunnel construction is being carried out with high determination, ensuring safety, quality and progress according to the plan.



Source: https://www.baogiaothong.vn/may-khoan-ham-tuyen-metro-nhon-ga-ha-noi-da-den-ga-cat-linh-192250307145749533.htm

Comment (0)

No data
No data

Same tag

Same category

Overseas Vietnamese player Le Khac Viktor attracts attention in Vietnam U22 team
The creations in the TV series 'Remake' left an impression on Vietnamese audiences
Ta Ma - a magical flower stream in the mountains and forests before the festival opening day
Welcoming the sunshine in Duong Lam ancient village

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product