Struggling with resettlement land fund

Việt NamViệt Nam03/05/2024

20240424_064732.jpg
Currently, there are 21 households affected by the Nghia Tu bridge approach road that have not been counted, examined for land origin, considered for resettlement, and there is no resettlement land to arrange for the households. Photo: QT

Lack of resettlement land

The Nghia Tu Bridge construction investment project was approved in March 2022. The construction investment scale includes an additional unit on the left of the Nghia Tu Bridge unit being invested in the project of Dredging, emergency flood drainage and preventing saltwater intrusion of Co Co River, Hoi An City and the road section leading to both ends of the bridge from the intersection with the Dien Nam - Dien Ngoc New Urban Planning Road to the intersection with DT603B Road.

The project has a total investment of 315 billion VND from the provincial budget and is scheduled to be implemented from 2022 to 2025. After more than 2 years, Nghia Tu bridge has just completed the construction of bored piles, pier M1, piers P1 and P2. The reason for this is that for a long time since the project was approved, the investor did not have a site for construction.

To solve the resettlement problem for 9 households affected by the construction of Nghia Tu bridge, the local government has managed to arrange 15 resettlement plots but scattered in 4 different separate locations on DT603B and DT607B roads.

Currently, there are 21 households affected by the Nghia Tu bridge approach road that have not been counted, examined for land origin, considered for resettlement, and there is no resettlement land to arrange for the households.

20240419_161310.jpg
Nghia Tu Bridge is currently implementing the construction of bored piles, abutment M1, piers P1 and P2 after a long time without construction site. Photo: QT

This reflects the passive state of the management agency in calculating the resettlement land fund to serve the construction of Nghia Tu bridge project and access road as well as more broadly public investment projects in the area.

In previous working sessions with Dien Ban town, the leaders of the Provincial People's Committee also mentioned that the problem that needs to be solved in Dien Ban is the lack of resettlement land fund.

Many projects are assigned to investors but only for the purpose of dividing and selling plots of land; while there is no land for resettlement for those projects. Urban areas invested by local authorities to serve resettlement in Dien Ban are too few compared to the development scale of the town.

Need a solution soon

Returning to the Nghia Tu bridge and approach road project, according to the Provincial Traffic Construction Investment Management Board (project investor), currently Thong Nhat residential area (Dien Duong ward) has arranged 22 resettlement lots (areas A2, A3) but there are 5 households that have not had their land cleared and 1 household that has illegally expanded for more than 2 years but has not been resolved.

Meanwhile, the Nghia Tu urban area project (70 lots) has not yet approved the construction drawing design - estimate and has not yet implemented compensation, site clearance and resettlement.

20240424_064914.jpg
Currently, Thong Nhat residential area (Dien Duong ward) has arranged 22 resettlement lots (areas A2, A3) but is also facing problems with site clearance. Photo: QT

Mr. Nguyen Van Thuong - Deputy Director of the Provincial Traffic Construction Investment Management Board proposed that priority should be given to resolving problems in Thong Nhat residential area before September 30, 2024 to have land to resettle households affected by the Nghia Tu bridge approach road.

In addition, it is also necessary to soon approve the design of construction drawings - estimates and carry out compensation, site clearance, and resettlement in Nghia Tu urban area to contribute to promoting the Nghia Tu bridge project and access road to complete on schedule.

Mr. Nguyen Xuan Ha - Vice Chairman of Dien Ban Town People's Committee informed that regarding Thong Nhat residential area, the locality and the investor are coordinating to complete procedures to extend the project progress. Regarding Nghia Tu urban area, the investment procedures are still in the process after the investment project was approved in November 2023. The locality will try to expedite the process soon to remove difficulties in site clearance for project construction.


Source

Comment (0)

No data
No data

Same tag

Same category

Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever
Phu Quoc - tropical paradise

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product