Faced with the serious landslide on National Highway 15C at Km88+750 in Pu Nhi commune (Muong Lat), causing traffic disruption on the route, the Department of Transport (GT-VT) urged the road management unit to mobilize vehicles to temporarily handle the situation and ensure smooth traffic here.
Thanh Hoa Road Management Joint Stock Company II mobilized machinery to handle incidents on National Highway 15C.
Due to the impact of storm No. 2, the floods in July and August 2024 and storm No. 3, the section Km88+750 - Km88+810 of National Highway 15C collapsed completely, with a depth of about 2.5m - 3m and a length of about 60m. On the right side of the route, the house of a resident has completely collapsed; on the left side of the positive slope, the headquarters of Pu Nhi Border Guard Station has also appeared with many large cracks in the yard, hall...
In addition, the section from Km88+810 - Km88+830 with a length of about 20m, the road surface has cracks with the risk of sliding. On the route, many large cracks have appeared on both the right and left sides of the route; the extent of the sliding arc cannot be determined accurately due to complex terrain and geological conditions.
On September 8, the Department of Transport announced traffic diversion through the location of negative slope landslide and subsidence of the road surface on National Highway 15C.
Serious landslide location on National Highway 15C.
To ensure traffic safety, on the afternoon of September 9, the Department of Transport coordinated with the Vietnam Road Administration and Thanh Hoa Road Management Joint Stock Company II to mobilize human resources and equipment to dig and handle the entire sunken roadbed with an average depth of 2m; restore the sunken roadbed and compact it; dig to replace the soil and restore the road surface structure, ensuring the route is clear.
Deputy Director of the Department of Transport Pham Van Tuan said: The Department has reported to the Ministry of Transport and the Provincial People's Committee about the subsidence of this road and proposed a temporary solution to reopen the road as soon as possible in accordance with the direction of the Provincial People's Committee.
In the immediate future, to ensure traffic, the Department reports to the Vietnam Road Administration for permission to implement a temporary solution on this route and continue to monitor and ensure traffic here.
Despite the difficult weather, the road management unit actively handled the landslide site.
If the weather conditions are favorable, the temporary treatment of the damaged road at Km88+750 in Pu Nhi commune will be completed before September 15, creating conditions for the entire National Highway 15C to be opened to traffic. In the long term, this is a slide that requires a solid solution, survey, design and a viaduct plan.
Lighthouse
Source: https://baothanhhoa.vn/khac-phuc-vi-tri-sat-lo-nghiem-trong-tren-tuyen-quoc-lo-15c-224403.htm