This afternoon (December 12), Politburo member, Secretary of the Hanoi Party Committee Bui Thi Minh Hoai - Head of the Steering Committee for the implementation of the Ring Road 4 Project - Capital Region chaired a meeting to listen to reports, review progress, implementation status, difficulties, obstacles in the implementation process and solutions to speed up the project's progress.
After about 17 months from the commencement date, 4 construction packages of component project 2.1 in Hanoi city have been simultaneously deployed by contractors on a route length of 48.35km, expected to be completed in the fourth quarter of 2025.
Regarding site clearance, up to now, Hanoi has approved and reclaimed over 780 hectares of land (reaching 98.44%). The city has basically completed resettlement areas and arranged resettlement for 337/818 households, equivalent to 41%.
Meeting to review the progress of the Ring Road 4 project.
The expected progress of site clearance and handover is before December 31, 2024. Regarding the adjustment of component project 1.1, the Hanoi Department of Transport has submitted to the City People's Committee to adjust the implementation time to the end of the second quarter of 2025.
In Hung Yen province, the site clearance of agricultural land, public land, and business land has been basically completed. Land has been recovered and handed over 215 hectares, reaching 95.1%. Component project 2.2, has organized 8 construction teams. Construction output reached about 28% of the contract value and over 97% compared to the approved progress.
At the meeting, Vice Chairman of the People's Committee of Hung Yen province Nguyen Hung Nam said: "One of the very difficult steps is that the problem of more than ten enterprises whose land was recovered in Hung Yen has been basically resolved.
Difficulties in land clearance, however, up to now we have basically issued decisions to recover land on property plans according to the provisions of the 2024 Land Law, Hung Yen will be determined to speed up this work, try to follow the direction of the Standing Committee of the Hung Yen Provincial Party Committee to try to complete it in December, then we will proceed to pay the people" .
Secretary of Hanoi Party Committee speaks.
In Bac Ninh province, the plan has been approved and land recovered for more than 363 hectares, reaching a rate of 97.28%. The basic completion and resettlement will be organized in the first quarter of 2025.
Concluding the conference, Secretary of the Hanoi Party Committee Bui Thi Minh Hoai acknowledged and highly appreciated the determination and concentrated efforts of Party committees at all levels and the political system of Hanoi city, Hung Yen and Bac Ninh provinces.
Local opinions.
The Secretary of the Hanoi Party Committee emphasized that this is a large project, not only with current difficulties, but certainly with new difficulties and problems arising, and requested that localities and related sectors uphold their sense of responsibility, compete to learn from each other's experiences, focus on discussing solutions, and proactively resolve them to ensure project progress.
“We each locality takes the initiative to completely remove difficulties. Comrades in the Steering Committee, we can learn from each other’s experiences and apply the law. This is not about applying the law, applying the law is very easy.
As I said, the officials who execute the law must follow it, but must apply it in a reasonable and emotional manner, in order to benefit the people the most and soon stabilize their lives and activities" - Secretary of the Hanoi Party Committee Bui Thi Minh Hoai said.
Source: https://vtcnews.vn/hop-kiem-diem-tien-do-du-an-duong-vanh-dai-4-vung-thu-do-ar913297.html