Resolutely carry out tasks to promote disbursement of public investment capital
The Ministry of Finance has just issued Document No. 3892/BTC-DT reporting to the Prime Minister on the implementation of the public investment plan using the State budget for 2 months and estimated 3 months of the 2025 plan.
Regarding the disbursement of planned capital in 2025, the Ministry of Finance said that the cumulative disbursement from the beginning of the year to February 28, 2025 was VND 44,811.2 billion, reaching 5.11% of the plan (VND 876,638.2 billion), reaching 5.43% of the plan assigned by the Prime Minister. Of which, the national target program (CTMTQG) is VND 2,191.5 billion (reaching 9.98% of the plan assigned by the Prime Minister).
Estimated disbursement from the beginning of the year to March 31, 2025 is VND 78,712 billion, reaching 8.98% of the plan, reaching 9.53% of the plan assigned by the Prime Minister. Of which, the National Target Program is VND 3,638.8 billion (reaching 16.57% of the plan assigned by the Prime Minister).
Estimated disbursement lower than the same period in 2024
Commenting on the disbursement of the capital plan, the Ministry of Finance said that the estimated disbursement by March 31, 2025 reached 9.53% of the plan assigned by the Prime Minister, lower than the same period in 2024 at 12.27%.
Results in the first 3 months of 2025, 13/47 ministries, central agencies and 36/63 localities had an estimated disbursement rate compared to the plan assigned by the Prime Minister above the national average. Some ministries, central agencies and localities had good disbursement rates (over 20%) such as: Voice of Vietnam (73.82%), Vietnam Bank for Social Policies (41.16%), Ministry of Public Security (23.73%), Women's Union (20.37%); Phu Tho (35.04%), Bac Kan (28.85%), Tuyen Quang (28.14%), Ha Nam (25.58%), Lao Cai (22.89%), Ha Giang (21.75%), Binh Dinh (20.25%).
However, in the first 3 months of the year, many ministries, central and local agencies have not yet disbursed (17 ministries, central agencies, including: Central Committee of the Vietnam Fatherland Front, Government Inspectorate, Vietnam Academy of Social Sciences, Ministry of Foreign Affairs, State Audit,...) or disbursed very low (16 ministries, central agencies and 06 localities disbursed less than 5%, including: Ministry of Science and Technology, Ministry of Health, Hanoi National University, Ho Chi Minh National University, Ministry of Industry and Trade, Ho Chi Minh City, Can Tho, Hanoi, Binh Phuoc, Ca Mau, Quang Ninh,...).
Resolutely carry out tasks to promote disbursement of public investment capital
To ensure that the disbursement rate of public investment capital in 2025 reaches the target of over 95% of the plan assigned by the Prime Minister, the Ministry of Finance proposes to implement a number of key recommendations and solutions as follows:
For the allocated capital, continue to resolutely implement tasks and solutions to promote the disbursement of public investment capital according to the direction and administration of the Prime Minister as prescribed in Official Dispatch No. 16/CD-TTg dated February 18, 2025 on urging the acceleration of allocation and disbursement of public investment capital in 2025, Decision No. 523/QD-TTg dated March 6, 2025 on establishing working groups to inspect, urge, remove difficulties and obstacles, and promote the annual disbursement of public investment capital at ministries, central agencies and localities.
For the NSTW capital that has not been allocated in detail after March 15, 2025, it will be recovered to allocate to projects that need capital to speed up the completion progress in accordance with the direction in Resolution No. 46/NQ-CP dated March 8, 2025 of the Government.
Drawing on experience in the organization and implementation of projects, especially for large-scale projects with complex technical requirements, spanning many localities, urgent construction time, difficult terrain and weather conditions, and shortage of raw materials, etc., it is necessary to strengthen inspection and supervision, clearly assign responsibilities, and closely coordinate among all levels and sectors to ensure scientific and effective work... according to the direction of the Prime Minister in Official Dispatch No. 673/TTg-CN dated September 5, 2024 on implementing key tasks to strive to complete 3,000km of expressways by the end of 2025.
At the same time, direct the investor, immediately after signing the contract, to coordinate with the contractor to implement the advance payment procedures according to regulations so that contractors with capital can immediately prepare the necessary conditions, supplies, and materials for the construction work of the project; speed up the acceptance process and complete the payment documents immediately after the volume is available to speed up the disbursement progress, ensuring that by the end of the payment deadline according to regulations (January 31, 2026), the projects will disburse all the assigned capital plan for 2025.
Lan Phuong
Source: https://baochinhphu.vn/giai-ngan-von-dau-tu-cong-3-thang-nam-2025-uoc-dat-898-ke-hoach-102250331164826224.htm