Dong Thap opens the way for the development of Sa Dec flower village

Báo Giao thôngBáo Giao thông09/01/2025

Every year, Sa Dec flower village (Dong Thap) attracts a lot of visitors, especially during holidays and Tet. Therefore, the locality is opening roads, creating favorable conditions for tourism development.


Mr. Vo Thanh Tung - Deputy Director of the Project Management and Land Fund Development Board of Sa Dec City (Dong Thap), the investor of the N7 road project, said that the project has a starting point intersecting with provincial road 848 and an end point connecting in the middle with the existing flower road.

Đồng Tháp mở đường phát triển làng hoa Sa Đéc- Ảnh 1.

Sa Dec City (Dong Thap) opens a 24m wide road to develop a century-old flower village.

The project is newly constructed with a level III plain road, passing through a number of households and production land of people in Tan Quy Dong ward and Tan Khanh Dong commune. Road N7 has a total length of about 1.2km, the roadbed is 24m wide, the road surface is 12m wide and the sidewalks on each side are 4m - 6m wide.

The total investment of the project is nearly 200 billion VND, including site clearance costs, construction costs, consulting costs and other costs. Of which, the value of the construction package is more than 90 billion VND.

Construction investment items include: foundation, road surface, sidewalk, Sa Nhien bridge, Ong Thung bridge, Muong Lo culvert, Cai Be canal culvert, Cao Thai Huong culvert, surface drainage system, public lighting system, trees, parking lot and welcome gate.

Once completed and put into use, the project will help the locality complete its infrastructure, meet the travel needs of local people and reduce traffic congestion, especially during holidays and Tet.

The project also contributes greatly to the renovation of the existing flower village road, in accordance with the planning of a traffic route combined with sightseeing for tourists from near and far.

"On the social side, the road construction investment project will increase its attractiveness to investors and strongly stimulate local socio-economic growth," Mr. Tung added.

Mr. Vuong Dao Anh Tuan, technical officer, Tuan Hien Company Limited (construction contractor) said that currently, the construction unit has basically completed the assigned construction items.

Specifically, about 95% of the longitudinal culverts have been constructed, 3/3 of the box culverts have been completed, Sa Nhien bridge has been completed and Ong Thung bridge is expected to have its girder installed before Tet.

The contractor is still continuing to fill sand and roll the roadbed. At the same time, the stones are being gathered at the construction site so that when the sandbed meets technical requirements, the next steps can be proactively carried out.

"The project started in early 2023 and to date, the estimated implementation volume has reached about 60%. The project is expected to be completed and put into use by the end of June 2025," said Mr. Tuan.



Source: https://www.baogiaothong.vn/dong-thap-mo-duong-phat-trien-lang-hoa-sa-dec-192250109155418345.htm

Comment (0)

No data
No data

Same tag

Same category

Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration
U90 veteran causes a stir among young people when he shares his war story on TikTok
Moments and events: April 11, 1975 - The battle in Xuan Loc was fierce.

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product