(NLDO) - On the afternoon of December 3, Mr. Nguyen Van Quang, Secretary of the Da Nang City Party Committee, inspected the Quang Da bridge and its approach roads.
Quang Da Bridge project connects Hoa Khuong commune, Hoa Vang district, Da Nang city with Dien Tien commune, Dien Ban town, Quang Nam province. At the inspection, the representative of the joint venture contractor said that the project has completed 53% of the contract value. The total disbursed amount for the project reached 121 billion VND.
The project is being implemented with the goal of completion on the occasion of the 50th anniversary of the Liberation of Da Nang City (March 29, 1975 - March 29, 2025) and to welcome the Party Congresses at all levels for the 2025 - 2030 term. It is expected that the Quang Da bridge and the approach road will be completed in March 2025.
The entire bridge is expected to be completed before March 10, 2025 and technically opened to traffic before March 29, 2025. At that time, the project is expected to complete 95% of the contract value.
Da Nang Secretary inspects Quang Da bridge project, afternoon of December 3
Mr. Phan Van Ton, Chairman of Hoa Vang District People's Committee, said that the construction progress basically meets requirements but the project has encountered some problems in site clearance.
The files within the clearance area have signed the site handover minutes, but there are still 2 files that have not been completed. At the frontage of National Highway 14B, there are still 16 files that need to be resolved.
The Hoa Vang District Land Clearance Council is focusing on resolving the issue with the goal of ensuring technical traffic clearance according to plan.
Quang Da bridge is expected to be technically opened to traffic before March 29, 2025.
Speaking at the inspection, Mr. Nguyen Van Quang, Secretary of the Da Nang City Party Committee, said that this project is a symbol of the close relationship between the two localities. This is not only a key project but also a clear demonstration of sustainable regional cooperation and connectivity.
"The investment of budget from one locality to another in this project is a noteworthy point, demonstrating a common sense of responsibility for comprehensive development" - Mr. Nguyen Van Quang emphasized.
According to the Secretary of Da Nang, this project is not simply a traffic project but also demonstrates the connection between Da Nang and Quang Nam, promising to promote socio-economic development and strengthen relations between the two localities.
The Quang Da Bridge and approach road project started construction in December 2023 with a total investment of VND 274 billion, invested by Da Nang City, and constructed by a joint venture of Xuan Quang Construction Joint Stock Company and Binh Dinh Traffic Design and Construction Joint Stock Company.
Source: https://nld.com.vn/cau-quang-da-bieu-tuong-cho-moi-quan-he-khang-khit-giua-da-nang-quang-nam-196241203202800729.htm