Vietnam.vn - Nền tảng quảng bá Việt Nam

Hung Duc Bridge is the longest on the North-South Expressway.

Báo Dân ViệtBáo Dân Việt09/03/2024


Hung Duc Bridge, the longest bridge on the North-South expressway on Lam River, before its closing day

Saturday, March 9, 2024 10:00 AM (GMT+7)

Hung Duc Bridge is nearly 4.1 km long, the longest bridge on the North-South Expressway with a total investment of more than 1,200 billion VND. Currently, the construction volume has reached 92-95%, expected to be closed on March 10 and completed in early May.

Video: Hung Duc Bridge, the longest bridge on the North-South expressway on the Lam River, before its completion.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 1.

Hung Duc Bridge with a total investment of more than 1,200 billion VND on the North-South Expressway, Dien Chau - Bai Vot section, nearly 4.1 km long, crossing Lam River is under urgent construction, expected to close on March 10 and be completed in early May.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 2.

The project has a total of 31 road bridges, including 23 bridges on the main route and 8 direct overpasses. Hung Duc Bridge is nearly 4.1 km long, this is the longest bridge on the North-South Expressway, Dien Chau - Bai Vot section.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 3.

Hung Duc Bridge is designed to be 17.5 m wide, with 4 lanes, a hard median in the middle and a design speed of 80 km/h.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 4.

The bridge was started in May 2022 by a consortium of contractors Dai Hiep Company Limited, Thai Yen Investment and Construction Joint Stock Company, Hoa Hiep Company Limited and Cienco 4 Group Joint Stock Company.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 5.

According to Dan Viet reporters, construction units are currently concentrating maximum machinery and human resources on the Hung Duc bridge construction site to complete it in early May. The bridge has a large design and complex structure, so many workers must concentrate highly to work.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 6.

Workers are focusing on cleaning the bridge surface to prepare for the next steps.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 7.

Mr. Tran Dinh Phong (of Thai Yen Company) said: "Despite the hot sun and sweat, everyone always encouraged each other to work hard to ensure the project's progress."

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 8.

Some workers use the shadows of large steel blocks to work.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 9.

According to the project company representative, the most difficult part of the construction of Hung Duc Bridge is the process of pouring concrete for the bridge abutments under the riverbed. Because Lam River has a deep bed and high water level. If the construction is not completed on schedule, the flood water from the river will greatly affect the construction.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 10.

Supplies, materials, machinery... are all transported by river. Currently, the contractor must mobilize modern machinery and large barges to serve the project in the best way.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 11.

Engineer Nguyen Quang Trung - Commander of Hung Duc Bridge project (Cienco 4 Group), said: "The unit in charge of construction from pier M0 to pier T13 has now completed the bridge deck and cast the cantilever from pier T1 to T13, and is casting the railing and median strip. Sections T15, T16 and T14 are completing the connection points, and can be closed in the next few days." Photo: PV

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 12.

There are only 2 more connection points to complete, and they can be closed in the next few days.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 13.

Close-up of the connection point on Hung Duc bridge across Lam river.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 14.

The bridge box girder is designed with several points of descent to check the bridge's electrical lines during use.

Cầu Hưng Đức dài nhất cao tốc Bắc - Nam trên sông Lam trước ngày hợp long- Ảnh 15.

The most difficult part is the construction of bored piles and piers in the middle of the river, which must be done quickly to overcome the flood. Each piers has 20 piles, more than 50 m deep. Currently, many bridge spans have been connected, the construction volume has reached 92-95%.

Set Agreement



Source

Comment (0)

No data
No data

Same tag

Same category

Southeast Asian fans react when Vietnam team defeats Cambodia
The sacred circle of life
Tombs in Hue
Discover the picturesque Mui Treo in Quang Tri

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product