Many sections of Highway 51 are currently damaged and degraded. |
The criticized units mainly failed to complete the construction drawing design work, were slow to deploy bidding for construction packages for one-step design projects, and did not fully update data on the disbursement software.
Notably, the disbursement rate by the end of March only reached 4.64% of the estimate.
The Department of Roads requires investors and project management boards to urgently speed up progress. For one-step design projects, contractor selection must be completed and construction contracts signed before April 30. For two-step design projects, construction drawing approval must be completed before April 20 and construction bidding organized before May 30.
After May 30, the Department will cut capital from slow-progressing projects to transfer to projects with better disbursement capabilities.