Close-up of the 'painful' road in Quang Ngai

Báo Tiền PhongBáo Tiền Phong31/10/2024

TPO - The Chu Van An road project (Quang Ngai city, Quang Ngai province) from Hai Ba Trung to Ngo Si Lien is only 876m long, but after 9 years of construction, only 150m has been completed. Currently, the construction site is still messy, "dusty in the sun, muddy in the rain" and it is unknown when it will be completed.


TPO - The Chu Van An road project (Quang Ngai city, Quang Ngai province) from Hai Ba Trung to Ngo Si Lien is only 876m long, but after 9 years of construction, only 150m has been completed. Currently, the construction site is still messy, "dusty in the sun, muddy in the rain" and it is unknown when it will be completed.

Close-up of the 'painful' road in Quang Ngai photo 1
In 2012, the People's Committee of Quang Ngai province had a policy to invest in the Chu Van An road project (section from Hung Vuong to Hai Ba Trung) and Nam Hai Ba Trung residential area with a total investment of about 320 billion VND.
Close-up of the 'painful' road in Quang Ngai photo 2
The project was initially assigned to the People's Committee of Quang Ngai City as the investor. In 2015, the People's Committee of Quang Ngai Province "changed its mind" and assigned both projects to Quang Ngai Investment, Construction and Service Trading Company Limited (QISC) as the investor. The project officially started in 2016.
Close-up of the 'painful' road in Quang Ngai photo 3
In 2020, the People's Committee of Quang Ngai province transferred the project to Quang Ngai City as the investor (construction of the section from Ngo Sy Lien to Hai Ba Trung).
Close-up of the 'suffering' road in Quang Ngai photo 4Close-up of the 'painful' road in Quang Ngai photo 5
Accordingly, Quang Ngai City divided the project into 10 packages, including 2 construction packages. However, by the end of 2023, the contractor had only completed about 150m of the road surface, the rest of the project was "shelved", the construction site was in disarray.
Close-up of the 'suffering' road in Quang Ngai photo 6
For many years, the project has been unfinished, people in the project area and traffic participants have had to endure the “dusty sun, muddy rain”. Many households subject to relocation have not been granted resettlement land (TDC) or compensated.
Close-up of the 'painful' road in Quang Ngai photo 7Close-up of the 'suffering' road in Quang Ngai photo 8Close-up of the 'painful' road in Quang Ngai photo 9
According to the reporter's records, there were no signs of construction at the construction site, only a few drainage pipes that had been left for too long, and weeds growing wildly.
Close-up of the 'painful' road in Quang Ngai photo 10
According to the People's Committee of Quang Ngai province, the goal of the Chu Van An extended road project is to connect the core area of ​​Quang Ngai city with the northern bank of Tra Khuc river, especially promoting the effectiveness of the Thach Bich bridge project. However, after nearly 12 years since the policy was issued and 9 years of launching, the project has not yet reached its completion date.
Close-up of the 'painful' road in Quang Ngai photo 11Close-up of the 'painful' road in Quang Ngai photo 12
The reason for the project's delay is due to problems with compensation, site clearance and some other reasons. Up to now, the project has only established and approved 5 compensation, support and resettlement plans, paying money to 56/90 households with a value of more than 23.5/33.7 billion VND.
Close-up of the 'painful' road in Quang Ngai photo 13Close-up of the 'painful' road in Quang Ngai photo 14Close-up of the 'painful' road in Quang Ngai photo 15
In addition, some cases have agreed to the compensation and resettlement plan. But in reality, the government has not arranged resettlement. Over time, problems have arisen when the land allocation plan issued ten years ago had a very low land use fee, now if the actual land allocation price increases, people do not agree.
Close-up of the 'painful' road in Quang Ngai photo 16
The project is stagnant, in 2023, the People's Committee of Quang Ngai province directed a comprehensive inspection of the project and proposed solutions to restart the project.
Close-up of the 'painful' road in Quang Ngai photo 17Close-up of the 'painful' road in Quang Ngai photo 18Close-up of the 'painful' road in Quang Ngai photo 19

The decision was issued in March 2024, but after 7 months the construction site has not changed. The fate of the road is still hanging in the balance with no completion date set.

The 100 billion bridge is still waiting to be built, people have to 'risk their lives' to cross the temporary muddy road
The 100 billion bridge is still waiting to be built, people have to 'risk their lives' to cross the temporary muddy road

Overloaded trucks
Overloaded trucks 'destroy' coastal road connecting Dung Quat Economic Zone - Chu Lai

Borrowing road for highway construction, Chinese contractor 'runs away' from repayment
Borrowing road for highway construction, Chinese contractor 'runs away' from repayment

Nguyen Ngoc



Source: https://tienphong.vn/can-canh-tuyen-duong-dau-kho-o-quang-ngai-post1687250.tpo

Comment (0)

No data
No data

Same tag

Same category

Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration
U90 veteran causes a stir among young people when he shares his war story on TikTok
Moments and events: April 11, 1975 - The battle in Xuan Loc was fierce.

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product