Optimizing lighting for Long Thanh airport terminal

Báo Giao thôngBáo Giao thông07/03/2025

The skylight is installed on both the body and wings of Long Thanh airport's passenger terminal, and is expected to last more than 4 months.


According to the Long Thanh International Airport Project Management Board, since the beginning of March, the joint venture of contractors has begun installing skylights on the roof of the Long Thanh International Airport passenger terminal. This type of glass helps the passenger terminal roof get natural light.

Tối ưu ánh sáng cho nhà ga sân bay Long Thành- Ảnh 1.

The roof of Long Thanh airport's passenger terminal is being installed with skylights.

Skylights are installed in both the body and wings of Long Thanh airport passenger terminal. The installation is expected to last more than 4 months.

Regarding the construction and equipment installation package of the Long Thanh airport passenger terminal, up to now, the terminal has completed all reinforced concrete underground and 4 floors. At the same time, the work of completing the erection of the roof steel structure, installing the vertical glass wall system, and the main roof of the terminal is being carried out.

The contractor has completed the erection of the central station roof steel. However, the central roof is heavy (about 5,500 tons), and the erection technique is complicated, so the units are adjusting it and are expected to lift the central station steel roof in mid-March 2025.

According to the Vietnam Airports Corporation (ACV), the Long Thanh International Airport construction investment project is simultaneously implementing items of component project 1 (construction of headquarters of state management agencies), component project 2 (works serving flight management), and component project 3 (essential works in the airport).

Of which, component project 3 is the largest and most important component project at Long Thanh airport with a total investment of more than 99,000 billion VND, including 16 construction and equipment packages.

Currently, the main item in the Component 3 project, the passenger terminal, is being accelerated in construction. Because the terminal has many complex items, high technical nature, designed with advanced and modern technology, it takes time to order and operate.



Source: https://www.baogiaothong.vn/toi-uu-anh-sang-cho-nha-ga-san-bay-long-thanh-192250307150521131.htm

Comment (0)

No data
No data

Same tag

Same category

'Patriotic baby' trend spreads across social networks ahead of April 30th holiday
Coffee shop causes fever with national flag drink on April 30 holiday
Memories of a commando soldier in a historic victory
The moment a female astronaut of Vietnamese origin said "Hello Vietnam" outside Earth

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product