After 8 years of stagnation, since the beginning of August 2024, the contractor for the Tam Trinh road expansion project (Hoang Mai, Hanoi) is implementing 4 construction phases, striving to complete the project in June 2026.
It is known that in 2012, the Hanoi People's Committee approved the investment policy for the Tam Trinh Road expansion project, with a total investment of VND 2,066 billion. The project started in 2016, but encountered difficulties in site clearance, so the progress was delayed. In December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion (an increase of VND 1,287 billion). At the same time, the project progress was adjusted from 2016 to 2026.
Source: https://www.baogiaothong.vn/toan-canh-du-an-mo-rong-duong-tam-trinh-len-40m-192241106180658536.htm