The contractor is urgently constructing the aggregate layer of the connecting route of the Can Tho - Ca Mau expressway through Ca Mau province.
According to the My Thuan Project Management Board, by December 9, 2024, the construction output of the Can Tho - Ca Mau expressway project reached 53% of the plan.
Up to now, about 360,000 m3/1 million m3 (load demand in 2024) has been mobilized for the project.
My Thuan Project Management Board and contractors have worked with Dong Nai, Kien Giang and Binh Duong provinces.
The locality has provided information on quarries that are producing stone that meets the project's technical requirements, ensuring sufficient supply for the project in 2024. Currently, the contractor has been mobilizing to the construction site.
Source: https://www.baogiaothong.vn/thi-cong-lop-da-cap-tuyen-noi-cao-toc-qua-ca-mau-192241227161339554.htm