220 kV Nam Sum – Nong Cong line is technically completed

Việt NamViệt Nam29/11/2024


220 kV Nam Sum – Nong Cong line is technically completed

The investor-level acceptance council - National Power Transmission Corporation (EVNNPT) held a Council meeting on the progress of energizing the 220 kV Nam Sum - Nong Cong transmission line project (part in Vietnam territory).

The 220 kV Nam Sum - Nong Cong transmission line project, invested by EVNNPT and managed by the Northern Power Project Management Board (NPMB), started construction in December 2021.

The project has a scale of 2 circuits nearly 130 km long with 299 pole positions, 99 anchorages, passing through Que Phong district, Quy Chau district (Nghe An province), Nhu Xuan district, Nhu Thanh district, Nong Cong (Thanh Hoa province).

The investor's acceptance council agreed that the project is eligible for energization.

The section through Nghe An province is 77.31 km long, including 174 column foundation locations. The section through Thanh Hoa province is 52.64 km long, including 125 column foundation locations. The entire route has up to 234 column foundation locations affected by forests.

This is an urgent project, invested in and built with the aim of importing electricity from the Nam Sum Hydropower Plant cluster (Laos) to Vietnam to meet the growing load demand of the Northern region's power system. At the same time, it concretizes the commitment between the Party and Government of Vietnam and Laos in strengthening energy cooperation.

Up to now, the entire foundation site has been handed over.

The members of the Acceptance Council said that the project was completed thanks to the close direction and management of the State Steering Committee for Key Energy Projects, the leaders of EVN and EVNNPT. Along with that, there were great efforts from NPMB and the units participating in the project.

The 220 kV Nam Sum – Nong Cong line serves the import of electricity from the Nam Sum Hydropower Plant cluster (Laos) to Vietnam.

to meet the growing load demand of the Northern region's power system.

At the meeting, the council members agreed that the project was eligible for energization, but also pointed out some shortcomings that needed to be addressed before energization.

Mr. Nguyen Ngoc Tan, Deputy General Director of EVNNPT, Chairman of the Investor-level Acceptance Council, acknowledged and highly appreciated NPMB and the units participating in the project for their great efforts to overcome many difficulties and challenges in site clearance, difficult construction terrain conditions, erratic weather conditions, etc. However, with the support of the Government, ministries, branches, EVN and local authorities where the power line passes through, the project has now been basically completed.

The project has been constructed according to design, ensuring technical requirements and meeting the conditions for technical energization.

The investor-level acceptance council approves the completion of items related to the power line. The investor-level acceptance council assigns the facility acceptance council to review the remaining contents and carry out related procedures to energize according to regulations.

Source: https://baodautu.vn/duong-day-220-kv-nam-sum–nong-cong-hoan-tat-ve-mat-ky-thuat-d231151.html


Comment (0)

No data
No data

Same tag

Same category

Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi
“Tunnel: Sun in the Dark”: The first revolutionary film without state funding
Thousands of people in Ho Chi Minh City wait to take Metro Line 1 on its inauguration day.

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product