According to the report of the General Department of Logistics and Engineering on the results of basic construction investment work in the period of 2021-2025, in which regarding construction planning work, the Department of Barracks (General Department of Logistics and Engineering) has appraised and reported to the Ministry for approval of planning documents of a number of units under the Ministry, ensuring quality.

Regarding the design of the model, the Barracks Department coordinated with the Design Institute (General Department of Logistics and Engineering) to adjust the design of the headquarters of the Military Command at the district level and was approved by the Ministry of National Defense; the design of the logistics warehouse model was reported to the Ministry; the design of the headquarters of the Military Command at the commune level, the barracks of the infantry regiment was completed, and reported to the head of the General Department of Logistics and Engineering... The Barracks Department also reported to the Ministry on the proposal for a specialized political classroom at the company and battalion levels.

Lieutenant General Vu Hai San gave a directive speech.

Regarding the management and use of budget for projects and works to ensure local military and defense tasks, according to reports from units, by the end of March 2025, nearly 70% of the projects and works in the 2021-2025 medium-term investment plan from budget sources to ensure local military and defense tasks had been completed.

Also at the meeting, the Finance Department reported on the results of the implementation of the 2021-2025 medium-term investment plan and the disbursement of construction investment projects in 2025. Regarding the state budget, based on the 2025 public investment plan and the budget assigned by the Government, the Ministry of National Defense has issued documents to deploy and assign detailed capital to the projects.

Concluding the working session, Senior Lieutenant General Vu Hai San requested that agencies and units continue to coordinate closely, speed up the progress and quality of basic construction investment projects and accelerate the disbursement of medium-term capital. Completed projects must be promptly inspected, audited, and settled to ensure strict compliance with procedures and legal regulations.

Working scene.

To ensure synchronization, savings, efficiency, and no loss or waste when adjusting local military organizations, and to meet mission requirements in the new situation, Deputy Minister Vu Hai San requested to temporarily suspend construction of unfinished projects and works; conduct review, acceptance of volume and settlement of value of completed volume. For projects and works that are completing investment procedures and have not yet started construction, the next steps will be temporarily suspended, allowing settlement of consulting work, site clearance, etc. that have been implemented.

The Finance Department shall preside over and coordinate with relevant agencies to work with specialized agencies of military regions, the Hanoi Capital Command, the Border Guard and localities to propose solutions to resolve legal and financial backlogs of projects and works and directions for implementing the next appropriate steps; report to the Head of the Ministry of National Defense for consideration and decision.

To strive to achieve the goal of basically completing the highest disbursement of investment capital in 2025 (98%), Senior Lieutenant General Vu Hai San requested the implementing agencies to review the investment plan for local military according to the direction of the Minister of National Defense. Study and adjust down newly opened projects in 2025, uncompleted projects under the Provincial Military Command, Provincial Border Guard Command, District Military Command to allocate capital for other projects that can be implemented and complete investment procedures, and deliver the budget before September 30, 2025.

Strengthen inspection and supervision to promptly synthesize and report to the Head of the Ministry of National Defense for consideration and resolution of difficulties and problems of units in implementing investment procedures, project implementation, and disbursement of investment capital.

News and photos: MINH MANH