TPO - It is expected that the Nguyen Khoi bridge - road project (connecting districts 7, 4 and district 1) with a total investment of more than 3,700 billion VND will start construction at the end of this year and be completed in 2027. Currently, the investor and related units are preparing to carry out site clearance work.
The Nguyen Khoi Bridge and Road Construction Project (connecting Districts 7, 4 and 1) has a total investment of about 3,735 billion VND, implemented by the city budget. Of which, the cost of site clearance is about 1,264 billion VND, the construction cost is about 1,748 billion VND. The project is invested by the Ho Chi Minh City Traffic Construction Investment Project Management Board.
On March 4, providing information on the project's progress, a representative of the Ho Chi Minh City Department of Transport said that from the first to the fourth quarter of this year, the project's adjusted Feasibility Study Report will be prepared, appraised and approved; compensation, support and resettlement will be carried out; and technical infrastructure will be relocated.
It is expected that the construction will start, compensation, support and resettlement will be completed; construction will be organized, acceptance will be conducted, the project will be completed and put into operation from the fourth quarter of 2024 to 2027 and the project completion settlement will be approved in 2028.
Overall perspective of Nguyen Khoi bridge - road project. |
“It is expected that in the first quarter of 2024, Ho Chi Minh City will complete investment preparation procedures to select a unit to prepare an adjusted feasibility study report. At the same time, the Department has coordinated with the People's Committees of Districts 1, 4, and 7 to review and update the planning and coordinate with the People's Committee of District 4 on the progress of site clearance work,” said a representative of the Ho Chi Minh City Department of Transport.
Nguyen Khoi Bridge - Road has a bridge section about 2.5 km long; the road section is more than 2.3 km long; the approach bridges have a total length of more than 1.3 km.
The main bridge branch will build a bridge over Te Canal, continue to go above ground by overpass along Nguyen Khoi Street, then cross Ben Nghe Canal to connect to Vo Van Kiet Street via two separate bridge branches N7 and N8.
The project has 8 pedestrian bridges connecting to the roads. According to the representative of the Ho Chi Minh City Department of Transport, the roads from the southern region to the center of Ho Chi Minh City are currently in a state of serious congestion. Main roads such as Nguyen Tat Thanh, Nguyen Huu Tho, Kenh Te bridge, Pham Hung street... are often congested, even during off-peak hours.
Therefore, the Nguyen Khoi bridge - road crossing the Te canal and Ben Nghe canal (along the Nguyen Khoi - D1 road axis) after completion will form the main road connecting the South area with the central area of Ho Chi Minh City. The project contributes to solving the traffic congestion at the existing Te canal bridge, Nguyen Huu Tho street, Nguyen Van Cu bridge, Chu Y bridge...
At the same time, this project gradually completes the traffic infrastructure system and technical infrastructure according to the planning, meeting the increasing traffic demand in the area....
Source
Comment (0)