How is the progress of the Tan Son Nhat T3 terminal project?

Người Lao ĐộngNgười Lao Động11/03/2025

(NLDO) - The project to build Terminal T3 of Tan Son Nhat International Airport has an investment capital of nearly 11,000 billion VND, and construction has so far reached about 95% of the volume.


On March 11, Vietnam Airports Corporation (ACV) announced that by early March 2025, the total construction volume of the T3 Passenger Terminal Project at Tan Son Nhat International Airport had reached about 95% and the progress was being controlled according to plan. The project is expected to be inaugurated on April 30, the 50th anniversary of the Liberation of the South and National Reunification Day.

According to the T3 Passenger Terminal Project Management Board, up to now, the architectural construction of the PTB passenger terminal has reached 100%, the architectural part is expected to be completed in March; the electrical equipment system, air conditioning and ventilation, fire protection, elevators and escalators, telescopic bridges, baggage conveyors, X-ray machines, etc. are all nearing completion.

The overpass system, aircraft parking area and external infrastructure are also completed. The expanded aircraft parking area is completed and is undergoing acceptance procedures for operation.

To inaugurate on April 30, a representative of the T3 Passenger Terminal Project Management Board informed that the project must be completed about 1 month in advance. This is a huge challenge.

In particular, it is necessary to complete unfinished items before March 31; organize test runs of technical systems from March 15...

Tiến độ đại công trình nhà ga T3 Tân Sơn Nhất hiện nay ra sao?- Ảnh 2.

Many construction items of Tan Son Nhat T3 terminal project have been completed and are in the process of completion.

The project to build passenger terminal T3 at Tan Son Nhat airport with a capacity of 20 million passengers/year includes 4 main items: Passenger terminal, high-rise parking garage combined with non-aviation services, overpass system in front of the terminal and aircraft parking lot, with a total investment of nearly 11,000 billion VND.

The new terminal will share the operating capacity between Long Thanh airport and Tan Son Nhat airport, supporting the overloaded T1 terminal, in order to improve the quality of passenger service.

Previously, social networks spread some information about the fact that from May 5, Tan Son Nhat airport will change the way terminals are allocated for domestic flights. Specifically, terminal T3 will serve Vietnam Airlines and Vietjet Air; terminal T1 will continue to operate but only for Bamboo Airways, Pacific Airlines, Vietravel Airlines, Vasco. The information also noted detailed instructions on how to get to terminal T3, 1 km from the existing terminal in Tan Son Nhat...

However, in an exchange with reporters from Nguoi Lao Dong Newspaper, Vietnam Airports Corporation (ACV) and Tan Son Nhat International Airport both confirmed that there has not been any official information regarding the exploitation of Tan Son Nhat T3 terminal.

Tiến độ đại công trình nhà ga T3 Tân Sơn Nhất hiện nay ra sao?- Ảnh 3.

A corner of Tan Son Nhat T3 terminal project (photo taken in December 2024)

Tiến độ đại công trình nhà ga T3 Tân Sơn Nhất hiện nay ra sao?- Ảnh 4.

Perspective of Tan Son Nhat T3 terminal



Source: https://nld.com.vn/tien-do-dai-cong-trinh-nha-ga-t3-tan-son-nhat-hien-nay-ra-sao-19625031110324357.htm

Comment (0)

No data
No data

Same tag

Same category

Ho Chi Minh City residents eagerly watch helicopters raise the national flag
This summer, Da Nang is waiting for you with sunny beaches.
Helicopters trained to fly and raise the Party flag and the National flag in the sky of Ho Chi Minh City
'Patriotic baby' trend spreads across social networks ahead of April 30th holiday

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product