(QNO) - On June 2, 2023, Quang Nam Newspaper published an article: "Construction of concrete road in group 8 (village 1, Tien Lanh commune, Tien Phuoc): People are concerned about the quality of the project". The article reported that when the construction unit had poured concrete for 70m of road, a petition arose from people in group 8 questioning and worrying about the quality of the project, so it had to stop.
Please read the previous article - "People are concerned about the quality of the project"
According to the content stated in the petition, the people of group 8 reported that the sand and gravel gathering site for the construction of the concrete road at the old site did not ensure quality, so they requested the contractor to gather materials at the new site.
On May 31, 2023, the construction unit continued to pour concrete on the road. After the relevant parties agreed in the minutes of acceptance of sand and gravel materials at the new staging area, the construction unit continued to pour concrete. According to the content agreed at this meeting, the Community Supervision Board assigned two people each day to supervise the construction. Tien Lanh Commune People's Committee also provided an additional set of cost estimates, designs and specific volume standards to the supervision team.
By the afternoon of June 4, 2023, Tien Lanh Commune People's Committee received information that a fight had broken out on this route between Mr. Vo Hong Vi - representative of the construction group and Mr. Vo Toan, a resident on supervisory duty. The Commune People's Committee temporarily suspended construction and directed the police to inspect and resolve the matter.
According to the incident report of Mr. Vo Toan (born in 1993), on June 4, 2023, as assigned by the people of group 8, Mr. Toan participated in construction supervision and was beaten by Mr. Vo Hong Vi. He was taken to the emergency room by relatives with multiple injuries to the head, chest and abdomen.
According to Mr. Toan's petition, at 7:00 a.m. on June 4, 2023, when he arrived at the construction site, he saw the excavator driver driving the excavator to scoop up sand and gravel from the old gathering place at Mr. Huynh Ngoc Ha's house, get on a pedicab and take it somewhere unknown.
After the excavator driver finished, he returned to work at the new material gathering area to mix the concrete. During the concrete mixing process, Mr. Toan reminded the excavator driver to pour the correct amount of material according to the commune's volume table.
At 3:00 p.m. the same day, the representative of the construction group, Mr. Vo Hong Vi, asked Mr. Toan to sign a commitment not to film or take pictures at the old sand and gravel site (which was discarded due to poor quality), and he signed to confirm. Afterwards, a fight broke out between Mr. Vi and Mr. Toan, which was stopped by people monitoring the construction site.
According to Mr. Toan, Mr. Vi's younger brother also got into a fight with him. After being beaten by these two people, Mr. Toan ran into a resident's house and reported to the commune police. After that, Mr. Toan returned home and was taken to the emergency room by his family.
In the complaint, Mr. Toan requested an assessment of his injury rate to have a basis for handling the subjects for the act of beating people on duty.
According to the investigation, related to the incident, on the evening of June 5, 2023, the People's Committee of Tien Lanh Commune held a meeting with the people of Group 8 to discuss solutions to continue the construction of the road. The people of Group 8 agreed to continue pouring concrete on the road on the morning of June 6, 2023.
In the minutes of the meeting ending at 10:30 p.m. on June 5, 2023, the representative of the construction unit, Mr. Vo Hoang Vi, requested that the people create conditions to continue pouring concrete on the road the following day. For sand and gravel materials, if the people check that they meet the conditions, the construction unit will pour concrete, otherwise it will stop. The incident between Mr. Vi and Mr. Toan is awaiting the decision of the police agency.
Chairing this meeting, Mr. Bui Sang - Chairman of Tien Lanh Commune People's Committee acknowledged and accepted the opinions of the people of Group 8 on the supervision of the construction quality. Mr. Sang requested the construction unit to follow the correct procedures and regulations and the people of Group 8 to coordinate and cooperate well with the construction unit in the supervision to continue the construction of the project to ensure the right progress, and soon complete the road for convenient travel.
Mr. Sang also requested the commune police to urgently investigate and resolve the case between Mr. Vi and Mr. Toan in accordance with the law; the Vietnam Fatherland Front Committee of the commune coordinates with the village to strengthen supervision of the construction.