The Vietnam Road Administration has just adjusted the temporary traffic organization plan for the Cau Gie - Ninh Binh expressway (section Km225+900-Km227+500) to ensure safe operation during the construction of phase 2 of the Phu Thu intersection investment project and the connecting road in Tien Hiep commune, Phu Ly city (Ha Nam).
According to Vietnam Expressway Corporation (VEC), temporary traffic diversion and organization on Cau Gie - Ninh Binh Expressway will begin on July 17.
For vehicles moving from North to South, when seeing the sign R.301d “Vehicles may only turn right” (at Km225+920), turn right onto the expressway exit, then go another 900m and follow the sign “Exit to Expressway” to continue south; or follow the sign “Entrance to Rest Stop” to use the service, then follow the connecting branch to exit the expressway to the south.
Similarly, for vehicles moving from South to North, when seeing the R.301d sign “Vehicles may only turn right” (at Km227+400), vehicles on the highway turn right onto the highway exit section. Then, vehicles travel another 50m, choose to follow the “Exit to the highway” sign or go through the “Entrance to the rest stop”.
Vehicles traveling on the highway at a speed of 120km/h must gradually reduce their speed as instructed when approaching the project area. The permitted speed when vehicles pass through the project construction area is not more than 60km/h.
VEC said that vehicles traveling on the route, when encountering problems or discovering unusual events, are requested to contact the operator via hotline 1900 1838 (available 24/7) to receive and process information.
BICH QUYEN
Source: https://www.sggp.org.vn/phan-luong-tam-thoi-tren-cao-toc-cau-gie-ninh-binh-tu-ngay-17-7-de-thi-cong-nut-giao-post749622.html