Urgently clear the highway rest stop

Báo Giao thôngBáo Giao thông28/05/2024


How does a rest stop work?

According to Giao Thong Newspaper's reporter, in addition to the overloaded rest stop on the Ho Chi Minh City - Long Thanh - Dau Giay Expressway (Km42), up to now, on the expressway sections from Ho Chi Minh City to Nha Trang (Khanh Hoa), there have been at least four more temporary rest stops in operation.

Bình Thuận: Gấp rút GPMB trạm dừng nghỉ cao tốc- Ảnh 1.

Cam Lam – Vinh Hao Expressway Rest Stop located at junction 709 (Thuan Nam district, Ninh Thuan) has parking and free water.

Specifically, on the Dau Giay – Phan Thiet expressway, at Km 69+500, the temporary rest stop is located on the left side of the route (intersection 765, Xuan Loc district). On the Vinh Hao – Phan Thiet expressway, the temporary rest stop is located at Km 199+750 (Ham Thuan Bac district).

On the Cam Lam – Vinh Hao highway, the temporary rest stop is located right at the 709 intersection (about 10km from Vung mountain tunnel). The waiting area and restrooms are made of containers, the parking lot is paved with thousands of square meters of asphalt. This is a rare temporary rest stop with an air-conditioned waiting room, providing free mineral water for drivers and passersby.

Because these are temporary rest stops, the parking area is limited, only capable of receiving cars and buses, and there are no fuel stations...

In contrast to the image of busy vehicles entering and exiting temporary rest stops, the planned locations of Phan Thiet - Dau Giay expressway rest stops (Km 47+700) and Vinh Hao - Phan Thiet expressway rest stops are still just empty lots.

Adjustment and supplement of planning

According to the planning in Binh Thuan province, there are four rest stops on two highways, each rest stop has a scale of about 2 hectares, now the planning has been adjusted to 5 hectares on each side.

Bình Thuận: Gấp rút GPMB trạm dừng nghỉ cao tốc- Ảnh 2.

On the expressway sections from Ho Chi Minh City to Nha Trang (Khanh Hoa), there is only the Ho Chi Minh City - Long Thanh - Dau Giay expressway rest stop (Km42), the rest are temporary rest stops.

On the Phan Thiet – Dau Giay Expressway, located at Km 47+500 (bordering Dong Nai and Binh Thuan provinces). Mr. Nguyen Cong Hop, Deputy Director of Phan Thiet – Dau Giay Expressway (Thang Long Project Management Board) said that he is coordinating with the locality to supplement the land use planning to hand over the site soon.

Opening bidding documents for Mai Son - National Highway 45 rest stop

Mr. Luong Van Long, Executive Director of Mai Son - National Highway 45 project (Thang Long Project Management Board) said that the bidding documents have been opened for the investment project to build and operate a rest stop at Km 329+700 (section through Dong Hoa commune, Dong Son district, Thanh Hoa province).

The project will build a pair of rest stops located on both sides at Km 329+700, in Dong Hoa commune, Dong Son district.

Of which, the station on the right side of the line has a total area of ​​about 39,184m2, the construction area of ​​the functional subdivisions of the station is about 24,500m2. The station on the left side of the line has a total area of ​​about 32,473m2, the construction area of ​​the functional subdivisions is about 24,500m2. The overall progress is expected to be 18 months from the date of signing the contract, the completion time of public service works is expected to be 12 months. Phuc Tuan

The two rest stops on the Vinh Hao - Phan Thiet highway are located at Km 144+560 (Tuy Phong district) and Km 205+092 (Ham Thuan Bac district). Up to now, Project Management Board 7 has handed over the site clearance stakes to the land fund development centers of the two districts to carry out site clearance compensation.

Tuy Phong District People's Committee has approved the results of contractor selection for the consulting unit for surveying cadastral maps and the consulting unit for checking and accepting cadastral maps for compensation and site clearance. Ham Thuan Bac District People's Committee has approved the technical design and estimate for surveying and drawing cadastral maps.

According to the Vinh Hao – Phan Thiet Expressway Management Board, it is expected that an investor will be selected in June 2024. Project Management Board 7 has worked with the People's Committee of Binh Thuan province and the districts and issued a document urging the locality to speed up procedures to hand over the site in July 2024. However, these two stations are currently facing difficulties in land use conversion procedures.

Mr. Pham Quoc Huy, Director of the Vinh Hao - Phan Thiet Expressway Management Board, said that the Km 205+092 rest stop has been added to the planning. The locality has not yet completed the updating of the Km 144+560 stop (Tuy Phong district) into the land use planning. "We are coordinating with the locality to soon complete the procedures," said Mr. Ha.

Explaining the reason for not yet completing the handover of the site, Mr. Tran Ngoc Hien, Vice Chairman of the People's Committee of Ham Thuan Bac district, said that the district had previously updated the location of the rest stop planning, established a survey file, and established a file as a basis for land counting and recovery. However, after supplementing the planning and moving to a new location, the land use planning had to be updated. "The land recovery must wait for the province's opinion on adjusting the land use plan, submit it to the Provincial People's Council for approval, and then implement the compensation and clearance steps," said Mr. Hien.

Meanwhile, Tuy Phong district representative said they will review the information and will respond later.

Reporting to the Government on the progress of investment in rest stops on highways in mid-May, the Ministry of Transport said that the Ministry had approved a network of rest stops on the North-South expressway in the East from Lang Son to Ca Mau with a total of 36 stations.

Up to now, 9 stations have been invested and are under construction; 1 station managed by the locality will be deployed when investing in the Huu Nghi - Chi Lang expressway; 2 stations on the route invested by the Vietnam Expressway Corporation are implementing investment procedures and 24 stations belong to component projects managed by the Ministry of Transport.

For 24 stations managed by the Ministry of Transport, 21 stations have selected contractors for consulting packages to prepare documents.

Of which, 8 stations on the North-South Expressway in the East, Phase 1, issued bidding documents on March 20, 2024, bid opening date is May 20, 2024, and it is expected that investors will be selected in June 2024. The construction time of the rest stops according to the bidding documents is 18 months, of which public service works are 12 months.

The Ministry of Transport will direct the Project Management Boards to negotiate with the winning investor to prioritize implementation to put public service works into operation within about 3 months after finding an investor.

For the remaining 13 stations, the Ministry of Transport is urgently developing a replacement circular to serve as a basis for implementation. To speed up the progress of selecting investors and implementation, the Ministry of Transport has reported and received permission from the Prime Minister to apply the simplified process and procedures for issuing circulars.



Source: https://www.baogiaothong.vn/binh-thuan-gap-rut-gpmb-tram-dung-nghi-cao-toc-192240528000144698.htm

Comment (0)

No data
No data

Same tag

Same category

Dien Bien girl practiced parachuting for 4 months to get 3 memorable seconds 'in the sky'
Memories of Unification Day
10 helicopters raise the flag in practice to celebrate 50 years of national reunification
Proud of war wounds after 50 years of Buon Ma Thuot Victory

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product