On the morning of February 9, the People's Committee of Thanh Hoa province held a ceremony to technically open the Van Thien - Ben En road project and the National Highway 1 connecting National Highway 45 project.
The Van Thien - Ben En road project was approved with a total investment of VND 1,181 billion, and construction started in August 2022; the road project connecting National Highway 1 with National Highway 45 with a total investment of VND 1,423.6 billion started in October 2022. To date, both projects have officially opened for technical traffic and put into operation.
Thanh Hoa Provincial People's Committee held a technical traffic opening ceremony for the Van Thien - Ben En road project.
The Van Thien - Ben En road project is 12.19km long, running through two districts of Nhu Thanh and Nong Cong in Thanh Hoa province. According to the design, the project has 4 lanes, the roadbed width is 33m, the median strip width is 5m; The land acquisition area is 69.2ha with 822 households affected.
This project is invested by Thanh Hoa Traffic Construction Investment Project Management Board, the construction unit includes a consortium of contractors: Central Construction Group Joint Stock Company, Minh Tuan Construction Investment Joint Stock Company, Huy Hoan Construction and Trading Investment Joint Stock Company, Bridge and Road Construction Investment Joint Stock Company.
The Van Thien - Ben En road project with a length of more than 12km has been opened to traffic and put into operation.
The project of connecting Highway 1 with Highway 45 is divided into 3 sub-projects. Of which, sub-project 1 (Ma River overpass and the road at both ends of the bridge from Km5+250-Km7+250) is invested by Thanh Hoa Traffic Construction Investment Project Management Board with a total investment of 655.4 billion VND.
Sub-project 2 (section Km7+250-Km14+603) is invested by Thieu Hoa District Construction Investment Project Management Board with a total investment of 454.7 billion VND; Sub-project 3 from the intersection with National Highway 1 to the beginning of Song Ma overpass (Km0-Km5+250) is invested by Hoang Hoa District People's Committee with a total investment of 306.7 billion VND.
Mr. Mai Xuan Liem, Vice Chairman of Thanh Hoa Provincial People's Committee, spoke at the technical opening ceremony of the two projects.
The project of National Highway 1 connecting National Highway 45 is invested with a roadbed width of 12m, road surface width of 11m; There are 6 bridges on the route, including 2 large bridges: Xuan Quang bridge over Ma river, more than 1km long (belonging to Sub-project 1) and the North-South expressway overpass in the East, more than 310m long (belonging to Sub-project 2). The total land acquisition area for the project is 54.37ha with 914 households affected.
Representative of the investor, Mr. Le Ba Hung - Director of Thanh Hoa Traffic Construction Investment Project Management Board said: During the implementation process, the construction progress of the projects was affected by the Covid-19 pandemic, storms, material shortages, escalating prices of raw materials, changes in policies in site clearance work, etc.
Xuan Quang Bridge across Ma River belongs to Sub-project 1 - Road project connecting National Highway 1 with National Highway 45.
However, under the direction and participation of all levels in site clearance work, the determination of construction contractors with the motto of overcoming the sun and rain, working in three shifts, four shifts, the projects have now been basically completed, ensuring sufficient conditions for technical traffic opening.
At the ceremony, Mr. Mai Xuan Liem, Vice Chairman of Thanh Hoa Provincial People's Committee emphasized that the two projects are connected to the North-South expressway in the East through Van Thien intersection and Thieu Giang intersection.
In particular, the Van Thien - Ben En road project connects the North - South expressway with Ben En National Park and is a new route connecting to the center of Ben Sung town, which will create conditions to expand development space to the Southwest for Nong Cong and Nhu Thanh districts, effectively exploiting the potential and advantages of tourism, ecology, resorts and entertainment services of Ben En National Park.
For the project QL1 connecting QL45 is an external traffic route directly connecting with QL1, QL45 and the North-South expressway (through Thieu Giang Interchange).
The two road projects put into operation contribute to facilitating people's travel and attracting investment.
"The completed route will shorten the travel time in the East-West direction when moving from the western districts of the province with National Highway 1, reduce traffic pressure via National Highway 45, National Highway 47, National Highway 217 to National Highway 1, ensuring service for the transportation of goods and passengers.
"Creating favorable conditions to attract investors to Phu Quy Industrial Park, Bac Hoang Hoa Industrial Park, Hoang Hoa district and Giang Quang Thinh Industrial Park, Thieu Hoa district", Vice Chairman Mai Xuan Liem pointed out the important role of the projects.
To maximize the potential, strengths, and investment efficiency of the projects, Vice Chairman of the Provincial People's Committee Mai Xuan Liem requested the project investor to complete all items on the traffic safety system and other related items to ensure technical and aesthetic requirements for project acceptance according to regulations in the first quarter of 2025, put the project into use to ensure efficiency, and well serve the travel needs of the people.
In addition, departments, branches and localities complete regional planning as a basis for promoting investment attraction and calling for investment in industrial parks along the route connecting National Highway 1 and National Highway 45. Speed up the progress to implement the Ben En Eco-tourism Resort Complex Project combining high-class entertainment services.
Source: https://www.baogiaothong.vn/thong-xe-ky-thuat-hai-tuyen-duong-nghin-ty-o-thanh-hoa-192250209110821683.htm