Accordingly, the Futabuslines – Thanh Hiep Phat joint venture (the joint venture of Phuong Trang Futabuslines Passenger Transport Joint Stock Company – Thanh Hiep Phat Company Limited) won the bid for the rest stops Km366+850 (PT) and Km366+920 (TT) of the National Highway 45-Nghi Son component project on the North-South Expressway, Eastern section.

The project has a preliminary cost of more than 328 billion VND; the state budget payment is 126 billion VND.

The project implementation progress is within 12 months, of which the time to complete public service works is 9 months. The project exploitation time after completing the investment work is within 25 years.

W-station comfort .jpeg
The Vietnam Expressway Administration (Ministry of Transport) has just approved the results of selecting contractors to build two rest stops on the National Highway 45-Nghi Son and Cam Lo-La Son expressways. Photo: N. Huyen

For the Km36+500 rest stop on the Cam Lo - La Son expressway, the T&T - 19-5 - Trung Phuong - Dong Bac joint venture (Joint venture of T&T Tourism Investment Joint Stock Company - 19-5 Thanh Hoa Joint Stock Company - Trung Phuong Private Enterprise - Dong Bac Trading and Construction Joint Stock Corporation) won the bid.

The project has a total implementation cost of more than 289 billion VND; paid to the state budget more than 15 billion VND; compensation, support and resettlement costs more than 7.4 billion VND.

The decision also clearly states that the actual project implementation time is 14 months, of which the time to complete public service works is 9 months. The project exploitation time after completing the investment work is 25 years.