Talking to Giao Thong Newspaper about the implementation of the Cho Moi - Bac Kan route investment and construction project, a representative of Project Management Board 2 (investor) said that currently, the survey and technical design work is being carried out, and is expected to be submitted to competent authorities for appraisal and approval in the period from October to November 2024.
According to plan, the Cho Moi - Bac Kan project will start construction in 2024 and be completed in 2026 (Illustration photo).
Notably, after the recent historic flood, the investor requested design consultants to monitor water levels and monitor flood developments on the Cau River. After reviewing the technical design and conducting field inspections, the parties agreed to make local adjustments to some locations.
Specifically, about 800m long of the Km 1+400 section (Thanh Binh Industrial Park, Thanh Thinh Commune, Cho Moi District) will be moved towards the residential area to avoid erosion of the Cau River.
About 1.5km at Km 4+500 (Thanh Thinh commune) will be moved with a deviation of about 10-60m from the old route to avoid affecting the existing stream flow.
About 2km at Km 11+500 (Thanh Mai commune) was adjusted to move about 5-10m from the old route to avoid the rising water edge of Quan stream.
"Based on actual and expected progress, the issuance of bidding documents for construction projects will be carried out in November 2024; the evaluation of contractor selection results and signing of construction contracts will be completed in December 2024.
According to the approved plan, the Cho Moi - Bac Kan route will be invested with a complete 4-lane scale, 22m wide roadbed, and a design speed of 80km/h. The total investment is over 5,750 billion VND.
Also in December 2024, the Cho Moi - Bac Kan project will start construction after completing the required procedures," informed a representative of Project Management Board 2.
According to PV's investigation, to ensure the investment progress of the Cho Moi - Bac Kan road project, recently, the People's Committee of Bac Kan province also issued a notice of the conclusion of the Chairman of the Provincial People's Committee Nguyen Dang Binh at the meeting to listen to reports on difficulties and obstacles for the GPMB Sub-project of the project.
Accordingly, local leaders requested the investor to consider and study the plan to implement the handover of stakes, markers, and GPMB boundaries... for each route section in September 2024 and early October 2024 so that units and localities of the province can organize the implementation of GPMB work contents according to schedule.
The investor is also requested to coordinate with the Departments, branches and sectors of Bac Kan province to exchange information on material usage plans, locations for dumping excess soil and rock, etc. and other related issues during project implementation.
"For the demand for common construction materials (sand, stone), Project Management Board 2 proactively provides the demand over time so that the relevant departments can coordinate and guide mining enterprises in the area, ensuring sufficient supply for the project according to the plan to make the most of local materials and labor, contributing to reducing the total investment of the project," the announcement stated.
Source: https://www.baogiaothong.vn/lua-chon-nha-thau-thi-cong-du-an-cho-moi-bac-kan-trong-thang-12-192240923184214476.htm