TPO - The Ring Road 2.5 underpass through Giai Phong intersection is an urgent project to reduce traffic congestion, and is scheduled to be completed this year. The project has just completed one side of the tunnel through the intersection and is urgently constructing the remaining items.
TPO - The Ring Road 2.5 underpass through Giai Phong intersection is an urgent project to reduce traffic congestion, and is scheduled to be completed this year. The project has just completed one side of the tunnel through the intersection and is urgently constructing the remaining items.
After more than 2 years of construction, the project has completed the access road in Dinh Cong area, and is focusing on constructing the tunnel between the intersection and the access road in Kim Dong street area. |
The Giai Phong - Kim Dong intersection in Kim Dong area is being fenced off to construct a closed tunnel, open tunnel and access road. |
With the access road in Dinh Cong area basically completed. |
Panoramic view of the Ring Road 2.5 underpass project through Giai Phong - Kim Dong intersection under construction |
Currently the project site is under construction day and night. |
In the middle of Kim Dong Street, there is now an open tunnel dug nearly ten meters deep. |
Although it is a key project of the city, the joint police - transport sector agreed and required the investor and contractor to implement the plan: Construction while ensuring traffic on the road. |
The project has recently completed one side of the tunnel at the intersection and removed the fence to widen the roadway for convenient traffic at the end of the year. |
Speaking to Tien Phong reporter, the representative of the investor, the Hanoi Traffic Construction Investment Project Management Board, said that the Ring Road 2.5 tunnel project has so far completed about 60% of its output. Currently, the project is no longer facing any major difficulties in terms of site clearance and is focusing on underground construction.
Recently, the project has completed the construction of the main tunnel segments H3B, H4B... located on Giai Phong Street from the inner city to Ngoc Hoi. In the near future, the project will proceed with the construction of tunnel segments from H2B to H5B located on Giai Phong Street from Ngoc Hoi Street to the inner city.
"When constructing the tunnel segments on this road, the project had to erect fences, occupying the entire roadway in the direction of Ngoc Hoi - inner city. However, at the end of the year, there are many vehicles, so in order not to affect people's travel, the fences here will not take place from now until the peak travel season of Tet At Ty" - said a representative of the Traffic Department.
The tunnel has a total investment of 778 billion VND. The project is scheduled to be completed in 2025, the investor said, this progress is being ensured.
Source: https://tienphong.vn/ham-chui-nut-giai-phong-kim-dong-hoan-thanh-60-khoi-luong-post1707944.tpo