To date, the Rach Mieu 2 Bridge project has been completed nearly 80%, 4% ahead of schedule. The Rach Mieu 2 cable-stayed main bridge is 24% ahead of schedule.
On January 25, My Thuan Project Management Board said that currently, contractors have mobilized more than 150 pieces of equipment and 583 technical staff and workers at 30 construction sites. All are determined to complete the project according to the direction of the Prime Minister and the Minister of Transport.
Rach Mieu 2 cable-stayed bridge section is 24% ahead of schedule.
According to the My Thuan Project Management Board, during the Lunar New Year 2025, the units were determined and proactive in arranging and organizing the construction of the main items until the last day of the old year. In particular, during the Tet holidays, the contractor still carried out auxiliary work, concrete maintenance, road maintenance, ensuring safety...
Along with that, contractors organize rotating teams on the construction site to ensure that workers and engineers have Tet with their families.
At the same time, to complete the general tasks of the project according to the expected schedule: on April 30, the main Rach Mieu 2 bridge will be closed, in August 2025, the middle bridge will be closed , on September 2, the technical traffic will be opened, and before October 30, the main bridge and the entire project will be completed.
Asphalt concrete pavement of Rach Mieu 2 bridge project is about 4km.
Currently, the project is under construction on the entire route of about 14km, 100% complete of the embankment and treatment of weak soil. Contractors are unloading more than 10/14km, constructing the crushed stone layer for 9/10km, and paving asphalt concrete in each segment for about 4km. The entire route including the road and bridge on the Ben Tre side will be completed before June 30.
Regarding the bridge section, four bridges have been completed (Xoai Hot, My Tho, Tam Son, Ba Lai), and two bridges are under construction (Rach Mieu 2 main bridge, Song Ma). Of which, Song Ma bridge will be completed before June 2025.
During Tet holidays, the contractor still maintains construction teams on site.
Rach Mieu 2 Bridge has completed 100% of the tower body P19, P20. At the same time, the contractor has completed the K10 girder block (K10 has 13 blocks) at the cable-stayed pillars P19, P20; has completed the SK11 girder block on the anchor pillars P18, P21. The contractor has installed and tensioned the cable-stayed cables for 88/112 bundles.
Rach Mieu 2 Bridge project is divided into 6 construction packages, started on March 28, 2022, expected to be completed by the end of 2025, with a total investment of 6,810 billion VND.
The project starts at the intersection of National Highway 1 and Provincial Road 870 in Chau Thanh District, Tien Giang Province; the end point connects to National Highway 60 at the Ham Luong Bridge approach road in Ben Tre City, Ben Tre Province.