The unfinished trillion-dollar road is full of trash and dust.

Báo Tiền PhongBáo Tiền Phong11/02/2025

TPO - The investment project to build the 2.5-meter road in Hoang Mai district (BT project), with a length of 2,061m and a total investment of 1,317 billion VND, has been delayed for more than 10 years and has just been directed by the Chairman of the Hanoi People's Committee to be resolved. However, up to now, the investor has not been able to continue construction.


TPO - The investment project to build the 2.5-meter road in Hoang Mai district (BT project), with a length of 2,061m and a total investment of 1,317 billion VND, has been delayed for more than 10 years and has just been directed by the Chairman of the Hanoi People's Committee to be resolved. However, up to now, the investor has not been able to continue construction.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 1
Recently, the Office of the Hanoi People's Committee issued Notice No. 29/TB-VP on the Conclusion of Chairman of the People's Committee Tran Sy Thanh at the meeting to listen to reports on the progress of implementation and problems in 2 traffic construction investment projects in the form of BT: Investment project to build traffic roads surrounding the Chu Van An memorial area, Thanh Tri district and Investment project to build Ring Road 2.5 (Dam Hong section - National Highway 1A), Hoang Mai district.
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 2
Regarding the investment project to build the Ring Road 2.5 (Dam Hong - National Highway 1A section), Hoang Mai District, the Chairman of the City People's Committee requested to consider and respond definitively to the complaints and denunciations of citizens related to the Counterpart Project and the BT Investment Project to urgently complete the project, along with putting into operation the Investment Project to build the underpass between the Ring Road 2.5 and Giai Phong Road...
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 3

According to Tien Phong reporters, the project is still "inactive", many areas have become spontaneous landfills. Many sections of the route are covered in dust day and night, making people angry.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 4
The above-mentioned investment project to build Ring Road 2.5 is implemented based on the terms signed in BT Contract No. 01/2014/HDBT (January 2014) and the Contract Appendix signed in 2017 between Party A - Hanoi People's Committee and Party B - consortium of Hanoi Housing and Urban Development Business Joint Stock Company, Hoang Ha Construction Company Limited (investor).
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 5
It is known that according to the BT contract, the investor will carry out the construction of 2.1km of road, in return the investor will be assigned a land area of ​​about 135.8ha to build the new urban area expanding the North and Northwest of Dai Kim - Dinh Cong. However, although the land has not been assigned to implement the project to recover capital according to the BT contract, the investor has sold it in the form of signing a capital contribution contract for many years now. This is the reason why dozens of customers have complained, even filed a complaint accusing the investor of fraud and property appropriation.
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 6

Informing Tien Phong newspaper, the investor consortium said that the construction project of the 2.5 Ring Road from Dam Hong to National Highway 1A has been behind schedule for many years due to land acquisition problems, not due to the investor's fault. The BT contract expired on June 30, 2018. The Hanoi People's Committee approved in principle the extension of the BT contract. However, the contract has not been extended according to regulations. Therefore, since 2020, the investor consortium has had to temporarily suspend construction due to the expiration of the BT contract. This has resulted in additional project management costs, unpaid interest costs, etc., causing losses to the investor.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 7
Notably, although the project has been implemented for more than 10 years and invested nearly 574 billion VND, the investor consortium has not yet received payment or land allocation from the competent authority to implement the project to recover capital according to the BT Contract...
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 8

"This is one of the very few BT projects in Hanoi that has not been paid for by another project, causing many difficulties for businesses," the investor informed.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 9
Regarding the new urban area project expanding the North and Northwest of Dai Kim - Dinh Cong, the Hanoi Inspectorate has issued a notice on handling complaints and petitions related to investors. The Inspectorate said that on November 28, 2018, the Hanoi People's Committee issued a decision approving the overall adjustment of the 1/500 scale detailed planning for the expansion of the North and Northwest of Dai Kim - Dinh Cong.
Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 10

The City People's Committee has not yet paid the investor with land funds at the project. The City Inspectorate recommends that the City People's Committee assign the Department of Natural Resources and Environment to review the corresponding land fund and determine the corresponding land area of ​​the Ring Road 2.5 construction project, and report to the City People's Committee.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 11

Investor's executive office and machinery are not working due to waiting for BT contract extension.

Hanoi: The unfinished trillion-dollar road is full of trash and dust, photo 12

Unfinished project becomes garbage dump.

PVTS Group



Source: https://tienphong.vn/ha-noi-con-duong-nghin-ti-dang-do-ngap-rac-va-bui-mu-mit-post1716113.tpo