The bridge over the river connecting Nghe An and Ha Tinh provinces before its completion

Báo Tiền PhongBáo Tiền Phong09/03/2024


TPO - After more than 2 years of construction, the Hung Duc bridge over the Lam River connecting Nghe An and Ha Tinh provinces on the North-South Expressway is gradually being completed. The bridge is expected to be closed in the next few days and will be completed by the end of April 2024.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of completion photo 2
After 2 years of construction, the bridge is now nearly complete. To date, the work volume has reached 95%. Hung Duc Bridge is expected to be closed in the next few days and completed before April 30.
The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 3

According to the design, Hung Duc Bridge has a total of 90 spans. Of which, the Lam River overpass consists of 5 spans, constructed using cantilever bridge technology with a large span of up to 120m. The width of the bridge is 17.5m with 4 lanes, with a hard median strip in the middle.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 4

The overpass over Lam River is 510m long, followed by the overpass over La Giang River (Ha Tinh) which is 147m long. In addition, on the Ha Tinh side, there is more than 2.2km of road leading to the bridge designed as a viaduct instead of a road.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 5The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of completion photo 6
Engineer Nguyen Quang Trung (in charge of Hung Duc Bridge of Cienco 4 Group Joint Stock Company) - said that the most difficult part of the construction of Hung Duc Bridge is the pile driving stage in the middle of Lam River. Each bridge pier is driven with 22 piles, with a depth of minus 50m.
The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 7
The construction of the foundation of the Lam River pier also identified difficulties when the Lam River water level rose erratically. Workers had to work quickly to avoid the flood season.
The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 8The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 9
"There are two more connection points on the Lam River to complete, the bridge will probably be closed in the next few days," said engineer Nguyen Quang Trung.
The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 10The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of completion photo 11

In Ha Tinh province, a 2.2km long approach bridge has been completed.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of completion photo 12The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 13

In recent days, Hung Duc bridge construction companies have been urgently mobilizing machinery and workers to complete the bridge on schedule.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 14

At the construction site, workers are working busily.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 15

At the junction between the spans on the river, workers are doing the final steps to pour concrete to close the bridge in the next few days.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 16The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 17

In addition to focusing on construction at the remaining connection points on the river, workers of Hung Duc bridge construction companies also cleaned the bridge surface to carry out the next stages such as making railings, paving the road surface and auxiliary works.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of closing photo 18

After 2 years of construction, Hung Duc Bridge has taken its shape. After completion and put into use, Hung Duc Bridge is the 5th bridge across Lam River connecting Nghe An and Ha Tinh provinces. Previously, there were 4 bridges put into use including: Ben Thuy Bridge 1,2, Cua Hoi Bridge and Yen Xuan Bridge.

The bridge over the river connecting Nghe An and Ha Tinh provinces before the day of completion photo 19

The final stages of the bridge are being worked on by contractors mobilizing barges, tower cranes, and cranes for construction, soon to be closed and put into use.

Shapes of bridges through forests and mountains on the North-South highway
Shapes of bridges through forests and mountains on the North-South highway

Suffocating when traveling on Nghi Son - Dien Chau highway
Suffocating when traveling on Nghi Son - Dien Chau highway

Close-up of Vo Van Kiet road connecting Ho Chi Minh City - Trung Luong expressway, not completed in 8 years
Close-up of Vo Van Kiet road connecting Ho Chi Minh City - Trung Luong expressway, not completed in 8 years

Ngoc Tu



Source

Comment (0)

No data
No data

Event Calendar

Same tag

Same category

Same author

No videos available