TPO - The Hoa Lien - Tuy Loan Expressway Project (Da Nang City) is 11.47km long and is under construction, so the narrow road is even more difficult to travel on. Not only is it jammed before Tet, these days, cars passing through the dusty, sunny and muddy road still have to line up, slowly "crawl" little by little.
TPO - The Hoa Lien - Tuy Loan Expressway Project (Da Nang City) is 11.47km long and is under construction, so the narrow road is even more difficult to travel on. Not only is it jammed before Tet, these days, cars passing through the dusty, sunny and muddy road still have to line up, slowly "crawl" little by little.
The Hoa Lien - Tuy Loan expressway construction project is part of the North - South expressway in the east, passing through 3 communes: Hoa Lien, Hoa Son, Hoa Nhon (Hoa Vang district, Da Nang city).
The route is being built by upgrading the National Highway 1 bypass.
Cars are crowded on the Hoa Lien - Tuy Loan road under construction. Not only trucks and containers move at a snail's pace, but private vehicles also move slowly because the road is both crowded and bad, with many "potholes". Before Tet, to reduce pressure on this road, authorities have diverted private vehicles from the exit of the Da Nang - Quang Ngai highway towards the city center. Photo: Thanh Hien. |
The distance between the cars is close together. Mr. Hoang Anh (Da Nang City) sighed because it takes a lot of time to go through this route. "I don't dare to go fast on the open section because of the bumpy "potholes" and "elephant holes", he said. |
After Tet, the road is still jammed with vehicles. According to records, heavy trucks continuously circulate on the route in both directions North and South. Every day, thousands of vehicles pass through here. |
According to the Ho Chi Minh Road Project Management Board (PMB), the Hoa Lien – Tuy Loan Expressway construction project will start in September 2023 and is scheduled to be completed in December 2025. The project site has been handed over 99.7%. |
At the inspection of the route at the beginning of the year, Secretary of the Da Nang City Party Committee Nguyen Van Quang requested functional units to hand over the site to the construction unit in February 2025. For households that have been supported and guaranteed the regime but still refuse to hand over the site, they will be handled according to regulations. |
Vehicles jostle and squeeze the road. On sunny and windy days, this road is dusty, and when it rains, it is muddy, making it difficult for vehicles to pass. |
"Taking advantage of the nice weather at the beginning of the year, the construction unit must make efforts to speed up the progress. Ensure that the main route is open by August 30 and the entire route is open by December 30," Da Nang City Party Secretary Nguyen Van Quang requested. |
This expressway starts at Hoa Lien intersection (part of La Son - Hoa Lien expressway section), ends at Tuy Loan intersection connecting to Da Nang - Quang Ngai expressway. In the photo: A section of La Son - Hoa Lien expressway. |
Source: https://tienphong.vn/o-to-nhuc-nhich-tung-chut-mot-qua-tuyen-hoa-lien-tuy-loan-post1714489.tpo