Hanoi ready to start construction of Ring Road 4 project on June 25

Người Đưa TinNgười Đưa Tin20/06/2023


Site clearance exceeded plan, reaching 81.62%

On the afternoon of June 20, Secretary of the City Party Committee Dinh Tien Dung - Head of the Steering Committee for the investment project to build Ring Road 4 - Hanoi Capital Region inspected the actual situation and progress of the project implementation.

Secretary of the City Party Committee Dinh Tien Dung and the delegation inspected the actual construction site No. 1 (intersection between Ring Road 4 and Thang Long Boulevard, km28+900, in Song Phuong commune, Hoai Duc district) and construction site No. 3 (intersection of the southern axis at km45+700, in Tam Hung commune, Thanh Oai district).

Reporting on the implementation of preparations for the groundbreaking ceremony of the Ring Road 4 construction investment project - Hanoi Capital Region at the meeting, the representative of the Hanoi City Traffic Construction Investment Project Management Board said that, up to now, districts in Hanoi have recovered land and handed over 651.33/798.043ha (81.62%).

Total number of tombstones moved: 6,035/10,039 (reaching 60.12%). Total approved amount: 4,626.79 billion VND.

Event - Hanoi is ready to start construction of Ring Road 4 project on June 25

Scene of the inspection of the actual situation and progress of the implementation of the Ring Road 4 project.

Regarding the selection of contractors for construction packages, the investor - Hanoi City Traffic Construction Investment Project Management Board has completed the selection of contractors for construction packages, project supervision consultants for the parallel road project and is organizing the preparation of construction drawings for approval and implementation of construction immediately after the project starts and has now met the conditions to start construction on the entire route.

Up to now, the districts have handed over the site to the Hanoi City Traffic Construction Investment Project Management Board, including the starting location for the contractor to organize the implementation of the site clearance for the project to start from June 18, 2023, expected to be completed before June 20, 2023, and eligible to start construction on June 25, 2023.

Event - Hanoi is ready to start construction of the Ring Road 4 project on June 25 (Photo 2).

Representative of the Project Management Board for Investment and Construction of Traffic Works in Hanoi City.

Reporting at the meeting, representatives of the leaders of 7 districts where the Ring Road 4 project passes through said that, up to now, the site clearance work is exceeding the city's plan and all show high determination in the project implementation process.

Specifically, the Ring Road 4 - Capital Region project passing through Me Linh district has a total length of 11.2km and up to now, 99.2% of the agricultural area has been cleared.

Regarding resettlement land, Me Linh district has 458 households needing site clearance and the district has planned compensation and site clearance for over 88% of the resettlement volume.

The progress of the resettlement area construction is on schedule. Me Linh District said it is determined to achieve the target set for the Ring Road 4 project and there are no problems in the implementation process.

Dan Phuong district has a 6.3km long Ring Road 4 project route and has completed 85% of the site clearance so far. The district has committed to handing over 100% of the site clearance by the end of the year.

Hoai Duc District informed that the Ring Road 4 route passes through 17.1km, and the land clearance rate has reached 84%. The district also expects the progress of the 2 resettlement areas to start construction in early and late July 2023 and will be completed in 3-4 months and there are currently no difficulties or obstacles in the implementation process.

Ha Dong District said that the project has 5.5km of land clearance in the district, and so far the site clearance has reached 84%. Thuong Tin District has reached 83.4% of the site clearance rate. Thanh Oai District has 9km of the project, and so far the site clearance has reached 82%. The district is committed to clearing the site on schedule so that by early July, the bidding and construction of the resettlement area can be organized.

Striving to recover 100% of the area in 2023

Through the actual inspection and conclusion, Secretary of the Hanoi Party Committee Dinh Tien Dung acknowledged, commended and highly appreciated the sense of responsibility, the drastic participation of the entire political system and the support of the people.

Event - Hanoi is ready to start construction of the Ring Road 4 project on June 25 (Photo 3).

Secretary of Hanoi Party Committee inspects project implementation progress.

According to the Secretary of the Hanoi Party Committee, in recent times, Hanoi City and the two provinces of Bac Ninh and Hung Yen have closely coordinated to implement the project as well as prepare for the project's commencement in June 2023.

Up to now, Hanoi has approved the project component 2, selected the contractor, so the project will start as planned on June 25. The two provinces of Hung Yen and Bac Ninh, due to slower approval and not yet selected the contractor, will organize the groundbreaking ceremony on the same day.

The Prime Minister is expected to attend the groundbreaking ceremony of the project in Hanoi. Hanoi Radio and Television will coordinate with the television stations of Hung Yen and Bac Ninh provinces to broadcast live the groundbreaking ceremony of the Ring Road 4 - Capital Region project.

Regarding the groundbreaking ceremony, the Secretary of the City Party Committee directed city, district and county agencies to continue to prepare carefully for a successful organization, in the spirit of ensuring the groundbreaking ceremony is organized synchronously at 4 locations, solemnly, economically, concisely, substantially, avoiding formality.

The Secretary of the City Party Committee emphasized that the groundbreaking ceremony is just the beginning, an announcement of the results of the work in the past time, and it is important to continue carrying out the upcoming tasks of the project.

Event - Hanoi is ready to start construction of the Ring Road 4 project on June 25 (Image 4).

Hanoi Party Secretary Dinh Tien Dung speaks at the inspection.

“I would like to note that once construction has started, it must be done immediately, and once it has been done, it must be done continuously. The investor must require the contractor to prepare sufficient machinery and materials to organize the construction. All levels, sectors, each agency, unit and each comrade must consider the project implementation to ensure progress in accordance with the Resolution of the National Assembly and Resolution No. 15 of the Politburo, which is basically completed by 2026 and put into operation from 2027; consider this a political task; once determined, we must be even more determined to carry it out,” Mr. Dung stated.

The Head of the Steering Committee for the implementation of the Ring Road 4 project emphasized the significance and importance of the project and requested the 7 districts, agencies and units to continue to do better in site clearance, strive to mobilize and persuade to create consensus so that no cases have to be forced; complete resettlement so that 100% of households can move to new places of residence and complete the recovery of 100% of the area in 2023 .



Source

Comment (0)

No data
No data

Same tag

Same category

Wandering around Lach Bang beach village
Explore Tuy Phong color palette
Hue - The capital of the five-panel ao dai
Colorful Vietnamese landscapes through the lens of photographer Khanh Phan

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product