On February 6, according to the Management Board of the Land Clearance Compensation and Resettlement Support Project of Dong Nai province, by the end of January, more than 300 billion VND had been disbursed for sub-projects of land acquisition, compensation, support, and resettlement of the Bien Hoa - Vung Tau expressway project through Dong Nai province.
Many people have received compensation related to the Bien Hoa - Vung Tau expressway project.
Of which, for component project 1, nearly 122 billion VND has been disbursed out of the total capital of 800 billion VND in the 2023 capital plan, reaching more than 15% of the plan.
For component project 2, more than VND 190 billion has been disbursed out of the total capital of VND 182 billion planned for 2023, reaching more than 104% of the plan.
Regarding the site, this February, localities will hand over 22 hectares of land belonging to component project 1 and 28 hectares of land belonging to component project 2 for the contractor to continue construction.
Regarding construction work, for component project 1 (with two packages), up to now, package XL01 has not been able to be implemented due to lack of land.
As for the XL02 package, due to limited, discontinuous and narrow handover area, only the overpass was constructed. Up to now, 44/44 bored piles have been completed, and the super T girder and T4 pier foundations are being constructed.
Workers at the Bien Hoa - Vung Tau Expressway Component 2 project.
In component project 2, also due to the land area, the contractor has only constructed at some locations, the output reached about 140 billion/4,279 billion, equivalent to 3.27% of the contract value.
Of which, the bridge section has cast more than 100 girders, 4 bored pile construction teams have completed 219 piles. In addition, two pier construction teams have poured concrete for M1, M2 abutments of Da Vang bridge and T8, T9 pier bases of Vung Tau - airport branch bridge.
On the road section, the contractor deployed 5 construction teams of organic excavation, K95 soil filling, test drilling of soil cement piles, construction of culverts, and precast structures.
The Bien Hoa - Vung Tau Expressway Project started construction on June 18, 2023 with a total length of 53.7km passing through Dong Nai and Ba Ria - Vung Tau provinces. Of which, the section passing through Dong Nai province is more than 34km long, and through Ba Ria - Vung Tau is 19.7km.
The project is divided into three component projects, of which, component project 1 is 16km long and is managed by Dong Nai Provincial People's Committee; component project 2 is 18.2km long and is managed by the Ministry of Transport and component project 3 is 19.5km long and is managed by Ba Ria - Vung Tau Provincial People's Committee.