The residential area project on Nguyen Van Linh Street (Pleiku City, Gia Lai Province) was established in 2003. Up to now, the project implementation has had many shortcomings and is behind schedule. In particular, the resettlement compensation stage has not yet received 100% consensus from the people, and this is considered the biggest obstacle when implementing the project.
The Nguyen Van Linh residential area project agreed to approve the compensation plan for 39.74 hectares of land of 761 households and organizations. Of which, 434/761 households agreed to receive compensation, the remaining 327 households did not agree. Compensation support has been provided in 13 phases for 344 plots of land with a value of over 677 billion VND, 304 households have handed over the land.
Mr. Doan Huu Dung - Deputy Secretary of the City Party Committee, Chairman of the People's Committee of Pleiku City requested the People's Committees of the wards to complete the verification of the year of tree planting, the land area that has not been granted a Land Use Right Certificate... before February 15. The Land Fund Development Center coordinates to complete the compensation work in February, striving to complete the progress and open Nguyen Van Linh Street in June 2025.
The Nguyen Van Linh residential area project is identified as a key and driving force project of Gia Lai province. The project scale is 2,160 billion VND, of which only 260 billion VND is invested by the Central Government.
Another difficulty pointed out is that the project's ability to recover capital is also a question mark...
Currently, the project is only slowly constructing many sections of the route. It is noted that after Tet, all construction sites were deserted.
The Chairman of Pleiku City People's Committee also proposed solutions to complete the project soon, requesting members of the Steering Committee to urge and direct the project implementation and report periodically every 2 weeks.
During the implementation of the Project, it is necessary to report difficulties in each specific case for timely resolution; mobilize cases in Hoi Phu ward (from Nguyen Viet Xuan street to Nguyen Trung Truc street) to soon agree on the compensation plan and hand over the site for project construction.
Some images recorded at project sections with many unfinished construction sections.
Source: https://kinhtedothi.vn/gia-lai-giai-phap-thuc-hien-du-an-khu-dan-cu-duong-nguyen-van-linh.html