Vietnam.vn - Nền tảng quảng bá Việt Nam

Million-dollar square project extension still difficult to reach the finish line

Báo Giao thôngBáo Giao thông02/11/2024

Construction started in September 2022 and has been extended, but the project of the Central Square of Dam Ha District 28/1 (Quang Ninh) on an area of ​​5.23 hectares, worth over 158 billion VND, is still in disarray, unlikely to reach the finish line as planned.


Construction is slow and unfinished

In late October 2024, Giao Thong Newspaper reporters went to the construction site of the 28/1 Central Square project in Dam Ha district and noted that the entire construction site had only one bulldozer and a truck carrying materials from the outside.

Quảng Ninh: Dự án quảng trường triệu đô gia hạn vẫn khó về đích- Ảnh 1.

The entire construction site of the multi-million dollar Square project in Dam Ha district is devoid of equipment and construction workers.

Mr. L, the owner of an apartment next to the project construction site, said: People are looking forward to the completion of this project so they can have a place to sightsee, exercise, and walk around... However, for more than two years, we have only seen the project being constructed slowly and unfinished, causing soil and rocks from the project to flow out, affecting traffic, fields, and gardens...

In fact, many items at the project are unfinished. Typically, the road leading to the center of the square, according to the design, has an area of ​​6,510m2 and is still in the process of leveling and compacting. The lake area and the flower garden are only partially built, with grass growing in between.

Quảng Ninh: Dự án quảng trường triệu đô gia hạn vẫn khó về đích- Ảnh 2.

Most of the project items are unfinished.

The highlight of the Square project is the 8.8m high, 3.1m wide relief with a total area of ​​695m2, which has only been completed in its rough form.

Other items such as sales kiosks and equipment installation have not been implemented yet. Most construction items in the project are lacking in workers and equipment.

Difficult to ensure progress after extension

The Dam Ha District Central Square Project 28/1 is invested by the District Construction Investment Project Management Board (PPMB) with a total capital of 145.44 billion VND, after adjustment to 158.4 billion VND.

The project is built on an area of ​​5.23 hectares, located on Le Luong Street, Dam Ha Town. Items include: Square area, green park and landscape lake, technical infrastructure.

In particular, the central square alone has an area of ​​nearly 18,031m2, designed with 1 floor, 3.6m high, with yard, parking lot, fountain, relief, lighting, Led screen...

Quảng Ninh: Dự án quảng trường triệu đô gia hạn vẫn khó về đích- Ảnh 3.

Panoramic view of the multi-million dollar Square project located in the center of Dam Ha district.

The completed project will create a unique complex of buildings, attracting tourists to visit, creating the basis for forming an urban area with modern architectural space and landscape.

According to the decision, the project must be completed by September 2024. However, due to the unsatisfactory construction progress, on August 19, 2024, the People's Committee of Dam Ha district decided to adjust the implementation time to December 31, 2024.

However, up to now, the project has reached over 60% of the contract volume, disbursed 95,445/158,466 billion VND, reaching over 60%...

Explaining the reason for the current slow progress of the project, a leader of the Dam Ha District Construction Investment Project Management Board said it was due to a lack of filling materials. To carry out the project, about 20,000m3 of soil was needed for filling. However, due to many reasons, while the project was being implemented, the mine expired, so the extension procedure had to be carried out, slowing down the progress.

Along with that, the recent storm No. 3 also affected the project's progress.

Quảng Ninh: Dự án quảng trường triệu đô gia hạn vẫn khó về đích- Ảnh 4.

It will cost about 16 billion VND to complete this relief, but the project was only approved for about 4 billion VND, so the investor is struggling to find socialized sources.

In addition, a problem that arose in the project was the funding to complete the relief. During the project approval process, the investor only calculated the cost of the rough part of the relief at about 4 billion VND. However, when implementing the work, according to the latest calculations, to complete this relief, it would take about... 16 billion VND.

Speaking to Giao thong Newspaper, a leader of Dam Ha district’s functional agency said that the investor plans to mobilize social resources to cover the additional costs of the relief. Currently, the first step of the relief’s architectural competition has been completed and the people who will carry out the second step have been selected.

"It is expected that in early November, the district will arrange a meeting to mobilize social resources. However, there are few businesses in the area and they suffered heavy damage after storm No. 3, so it is very difficult to mobilize 12 billion VND. And so, we do not know when this relief will be completed," informed the leader of the professional agency of Dam Ha district.



Source: https://www.baogiaothong.vn/quang-ninh-du-an-quang-truong-trieu-do-gia-han-van-kho-ve-dich-192241030095648849.htm

Comment (0)

No data
No data

Same tag

Same category

Vietnam not only..., but also...!
Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration
U90 veteran causes a stir among young people when he shares his war story on TikTok

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product