Currently, the Bien Hoa - Vung Tau expressway has completed more than half of its construction. It is expected that the asphalt will be laid at the end of November when the rainy season ends.
On November 11, the People's Committee of Ba Ria - Vung Tau province issued Plan No. 263/KH-UBND to launch a peak competition to complete component project 3 of the Bien Hoa - Vung Tau expressway construction investment project phase 1 before December 31, 2025.
The highway through Ba Ria - Vung Tau has formed a route.
The plan is to respond to the peak emulation campaign "500 days and nights of emulation to complete 3,000km of expressway" according to Decision No. 1008/2024 of the Prime Minister.
Competition contents include creative labor, completing on schedule, exceeding plans, and ensuring project quality according to the direction of the Central and the province.
Construction, consulting and supervision to ensure quality, technique, aesthetics, environmental sanitation, labor safety, and create landscape for the project's development space after completion. Coordinate with local authorities to remove difficulties and obstacles related to construction materials and site clearance.
At the same time, research and apply science and technology, information technology, and modern management methods in the design, construction, operation, and management of highway projects, improving labor efficiency, shortening implementation time, saving resources and human resources...
The competition will be implemented from October 2024, with a preliminary review in December 2024 and a final review at the end of 2025.
Motorbikes and workers are reinforcing cement concrete on the route.
According to the report of the Cai Mep - Thi Vai Regional Traffic Project Management Board (investor), the Bien Hoa - Vung Tau Expressway component 3 project has basically completed 100% of the site clearance work. The completed volume has reached 51% of the project value, and it is expected that the asphalt paving will begin at the end of November when the weather is nice.
In 2024, the project was allocated nearly 1,200 billion VND of central budget capital, of which 690 billion VND was disbursed, reaching 58%.
Previously, during the survey visit to Bien Hoa - Vung Tau Expressway on November 2, Mr. Nguyen Cong Vinh, Vice Chairman of Ba Ria - Vung Tau Provincial People's Committee, requested the investor to coordinate with the contractor to control weekly, promptly take measures to increase compensation for delays to ensure the overall progress of the project. Accelerate the project's progress in the coming time.
"The project must make efforts to overcome difficulties and ensure technical traffic opening before April 30, 2025. At the same time, closely coordinate with the Ministry of Transport to promptly submit to the Government to arrange central capital for investment in the project according to regulations," said Mr. Vinh.
Highway construction output increases rapidly every day
Currently, on the entire Bien Hoa - Vung Tau expressway section through Ba Ria - Vung Tau province with a length of 19.5km, the consortium of 3 contractors is simultaneously implementing construction with more than 15 construction sites. Mobilizing 225 equipment and 415 personnel to deploy and spread out the work, the cumulative volume of work completed is about 51%.
Of which, Son Hai Company constructed 14.2km of road, currently deploying 5 construction teams with nearly 100 equipment and 200 personnel. Workers focused on constructing items: culverts, K95, K98 earth filling, crushed stone aggregate, cement-reinforced crushed stone aggregate layer, underpass, service road...
Company 703 constructed 5.3km of road and 2 overpasses, currently deploying 5 construction teams with nearly 75 equipment and 115 personnel. Focusing on culvert construction, K95, K98 earth filling, and crushed stone grading. Completed 18/18 bored piles of Km 48+224.74 bridge and is constructing piers (50% complete); completed 28/32 bored piles of Km 49+935.23 bridge.
Company 479 is constructing 9 bridges, currently deploying 6 construction teams with nearly 50 equipment and 100 personnel, constructing 7/9 bridges, of which 5 bridges are under construction with bored piles, pier bases and 1 bridge is under completion (Suoi Da bridge).
Source: https://www.baogiaothong.vn/cao-toc-qua-ba-ria-vung-tau-hoan-thanh-hon-mot-nua-cuoi-thang-11-tham-nhua-192241111102230176.htm