Can Tho plans to start upgrading National Highway 91 in April 2025. At the same time, urgently develop a construction plan, proactively source sand and stone materials to ensure the project progress from meeting to exceeding the set plan.
On January 7, Mr. Le Minh Cuong, Director of the Can Tho City Construction Investment Project Management Board, said that the Board is speeding up related procedures, and is expected to start the project to upgrade and expand National Highway 91 (section from Km0 - Km7) in Can Tho City (upgrading and expanding National Highway 91) in April 2025.
Upgrading National Highway 91 is expected to start in April 2025.
"We are also implementing the selection of contractors to implement the project packages," added the Director of the Can Tho City Construction Investment Project Management Board.
The project to upgrade and expand National Highway 91 was approved by the People's Committee of Can Tho City in July 2024. The Can Tho City Construction Investment Project Management Board was assigned as the investor.
Accordingly, the project is about 7km long. The starting point is at the intersection of Cach Mang Thang Tam - Hung Vuong - Tran Phu - Nguyen Trai streets in Ninh Kieu district. The end point is at the Km7 milestone in Binh Thuy district.
The total investment of the project is over 7,237 billion VND. Of which, compensation and resettlement support costs are over 5,556 billion VND, construction costs are over 1,302 billion VND, the rest are equipment costs, project management...
The project is invested in upgrading to a scale of 6 lanes, design speed of 60km/h. Project implementation period is from 2023-2027.
On January 2, Can Tho City People's Committee issued an official dispatch to implement the conclusion of the City Party Secretary regarding the project.
In the dispatch, the Chairman of the People's Committee of Can Tho City assigned the City Construction Investment Project Management Board to closely coordinate with contractors and relevant authorities to develop plans and proactively source materials, especially sand for filling, gravel, etc.
At the same time, research appropriate construction technical solutions to speed up progress, shorten construction time, strive to complete the project on schedule and exceed the set schedule.
Along with that, the investor, together with the City Land Fund Development Center and the districts where the project passes through, urgently complete legal procedures to carry out compensation, support, resettlement... to ensure sufficient conditions for the project to start construction on the occasion of the 50th anniversary of the Liberation of the South and National Reunification Day.
In particular, the units must complete compensation, resettlement support, relocation of technical infrastructure works and hand over 100% of the clean site for the project in 2025.
National Highway 91 connects Can Tho city to Tinh Bien border gate, An Giang province, 142km long. The starting point is in Ninh Kieu district (Can Tho city) and ends in Tinh Bien town (An Giang province).
The section passing through Can Tho is about 51km long. The first section from Km0 - Km7, the Ministry of Transport will hand over to the locality for management according to urban road regulations.
Source: https://www.baogiaothong.vn/can-tho-du-kien-khoi-cong-du-an-giao-thong-hon-7237-ty-dong-vao-thang-4-2025-192250107175034585.htm