Minister Tran Hong Minh: Efforts to bring Quang Ngai - Hoai Nhon Expressway ahead of schedule

Việt NamViệt Nam17/01/2025


Minister of Transport Tran Hong Minh inspected the Quang Ngai - Hoai Nhon expressway, requiring investors and contractors to be highly determined and complete the project ahead of schedule assigned by the Prime Minister.

Bộ trưởng Trần Hồng Minh: Nỗ lực đưa cao tốc Quảng Ngãi - Hoài Nhơn vượt tiến độ - Ảnh 1.

Minister Tran Hong Minh directs investors, contractors, and localities at the Quang Ngai – Hoai Nhon expressway construction site – Photo: L.D.

On the afternoon of January 16, Minister of Transport Tran Hong Minh inspected the construction site of the Quang Ngai – Hoai Nhon expressway project and praised the efforts of the investor and contractors at the construction site over the past two years.

Pay attention to progress, ensure highway quality

The Quang Ngai – Hoai Nhon Expressway Project is a national key project. Minister Tran Hong Minh requested the investor and contractor to make more efforts and determination to complete the expressway in accordance with the Prime Minister’s direction, contributing to connecting 3,000km of the North – South Expressway.

With the unfavorable weather and continuous rain for many months, the minister shared the difficulties with the contractor. At the same time, he acknowledged the flexibility, shifting the construction of the highway, and adapting to weather conditions.

Besides the requirement to concentrate equipment and construction personnel to bring the project to completion ahead of schedule, the minister also noted that the quality of the project must be put first.

The existing problems and obstacles in construction, especially the site clearance, need to be resolved by the provinces. Avoid small problems that greatly affect the progress.

Regarding the 3,200m long tunnel No. 3 (the longest tunnel of the North-South expressway in the east) located between Quang Ngai and Binh Dinh provinces, which is meeting the schedule, the minister requested to speed up the construction site, but must ensure the safety of people and property.

By October, the Quang Ngai - Hoai Nhon highway must be basically completed.

Mr. Ngo Truong Nam, General Director of Deo Ca Group Joint Stock Company (contractor), reported that the construction site always maintains 50 main construction teams. Of which, there are 25 road construction teams; 18 bridge construction teams and 6 tunnel construction teams with a total of more than 1,400 machines and equipment and nearly 4,000 employees working continuously.

Quang Ngai – Hoai Nhon Expressway has 3 road tunnels. Two tunnels have been opened, the remaining tunnel has reached 73% progress. It is expected that the tunnel will be opened by April 30. Of the 77 bridges on the route, 39 have had their girders installed.

After 2 years of construction, the cumulative project construction output reached 7,200/13,343 billion VND of construction and installation capital. The disbursement of capital allocated for 2024 reached over 99%.

Bộ trưởng Trần Hồng Minh: Nỗ lực đưa cao tốc Quảng Ngãi - Hoài Nhơn vượt tiến độ - Ảnh 3.

Adverse weather conditions force contractors to ensure highway progress – Photo: L.D.

Speed ​​up, exceed the progress assigned by the Prime Minister

Mr. Le Thang, Director of Project Management Board 2 (investor), said that the project progress is on schedule. The investor coordinates and urges the contractor to make efforts to complete ahead of schedule.

“Materials and equipment are ready. When the weather is sunny, we will speed up the construction of the entire project, ensuring the completion of the project as directed by the Prime Minister at the launching ceremony of the 500-day emulation movement to complete the North-South Expressway,” Mr. Thang affirmed.

After listening to the report, Minister Tran Hong Minh emphasized that the project is very important in the North-South expressway system in the East, connecting the expressway section that has been put into operation and the section under construction. The desire to complete the project soon to extend the North-South expressway is not only at the government level, but also among the people.

“The remaining volume is not much, and time is urgent. Investors and contractors need to focus on machinery and personnel to speed up construction, ensuring that the project is basically completed by October. The Prime Minister requested that it be completed by the end of the year, and we must strive to exceed the assigned schedule,” Minister Tran Hong Minh directed.

On the occasion of Tet, Minister Tran Hong Minh gave gifts, encouraged and shared with workers of contractors and sent New Year wishes to all workers working day and night at the construction site.

Bộ trưởng Trần Hồng Minh: Nỗ lực đưa cao tốc Quảng Ngãi - Hoài Nhơn vượt tiến độ - Ảnh 4.

Minister Tran Hong Minh gives gifts, encourages and shares with workers at the highway construction site - Photo: L.D.



Source: https://tuoitre.vn/bo-truong-tran-hong-minh-no-luc-dua-cao-toc-quang-ngai-hoai-nhon-vuot-tien-do-20250116194635531.htm


Comment (0)

No data
No data

Same tag

Same category

Same author

Figure

French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes
17-second video of Mang Den so beautiful that netizens suspect it was edited
The primetime beauty caused a stir because of her role as a 10th grade girl who is too pretty even though she is only 1m53 tall.

No videos available