Removing difficulties and speeding up the progress of Khanh Hoa project

Báo Giao thôngBáo Giao thông23/11/2024

Deputy Prime Minister Nguyen Hoa Binh inspected and requested the competent authorities and investors to focus on removing difficulties and speeding up the progress of the Khanh Hoa - Buon Ma Thuot expressway.


On November 23, Deputy Prime Minister Nguyen Hoa Binh inspected the situation and progress of the Khanh Hoa - Buon Ma Thuot Expressway Project. Accompanying him were Deputy Minister of Transport Le Anh Tuan and the investor of the project component 3.

Tháo gỡ khó khăn, đẩy nhanh tiến độ dự án Khánh Hòa - Buôn Ma Thuột- Ảnh 1.

Deputy Prime Minister Nguyen Hoa Binh inspects the progress of the Khanh Hoa - Buon Ma Thuot Expressway Project, component project 3. Photo: NH

At the construction site, reporting to the Deputy Prime Minister, the Dak Lak Provincial Management Board of Transport Construction Investment and Rural Development Projects (representing the investor) said that the Khanh Hoa - Buon Ma Thuot Expressway is divided into 3 component projects. Component project 1, managed by the Khanh Hoa Provincial People's Committee, is 31.5 km long and is scheduled to be completed in 2026.

Component project 2, managed by the Ministry of Transport, is 36.9km long and is scheduled to be completed in 2027. Component project 3, managed by the Dak Lak Provincial People's Committee, is 48km long and is scheduled to be completed in 2026.

Tháo gỡ khó khăn, đẩy nhanh tiến độ dự án Khánh Hòa - Buôn Ma Thuột- Ảnh 2.

According to the plan, by August 30, 2025, the progress of component project 3 will be open to traffic. Photo: NH

Regarding site clearance, as of October 30, the total volume of site clearance and handover work reached more than 99% (equivalent to 48.09/48.09km). Currently, there is only 1ha of drainage canal outside the main route being implemented due to the new addition to the land use planning of Cu Kuin district.

The relocation of technical infrastructure (electricity, water, telecommunications, etc.) is being carried out by localities. Regarding the dumping site for excess materials, according to the investor's assessment, it basically meets the demand, in which some locations belonging to component projects 2 and 3 are completing procedures to be used for the project.

To date, the construction volume has reached more than 26% of the contract value. Of which, package 1 has achieved more than 31%; package 2 has achieved more than 23% of the contract value; package 3 has achieved more than 29% of the contract value. According to the investor, the project progress is being accelerated by contractors, completed according to plan, meeting the set schedule.

Tháo gỡ khó khăn, đẩy nhanh tiến độ dự án Khánh Hòa - Buôn Ma Thuột- Ảnh 3.

During the inspection, the Deputy Prime Minister presented gifts to the construction contractors. Photo: NH

Deputy Prime Minister Nguyen Hoa Binh highly appreciated the Ministry of Transport, Dak Lak province, and Khanh Hoa province for their efforts, mobilizing resources, and overcoming difficulties to implement the project investment.

At the same time, we highly appreciate the investor, contractors, officers, engineers, workers and laborers who have worked actively and continuously to speed up the construction progress, striving to complete ahead of schedule for each construction item and the entire project.

The Deputy Prime Minister requested that the competent authorities and investors focus on resolving current difficulties of the project, and direct more resolutely to speed up the construction progress, while ensuring project quality, labor safety, and environmental sanitation.



Source: https://www.baogiaothong.vn/thao-go-kho-khan-day-nhanh-tien-do-du-an-khanh-hoa-buon-ma-thuot-192241123192728818.htm