Tra Ly dike renovation and upgrade projects have all met and exceeded the set schedule.
Thursday, August 10, 2023 | 15:44:17
459 views
According to information from the Provincial Agricultural Construction Investment Project Management Board, two projects to repair and upgrade the dike: Tra Ly left, section from K25+600 to K26+785, Thai Binh city and Tra Ly right, section from K7+000 to K7+700, Vu Thu district have been basically completed, ahead of schedule.
Construction of the left embankment of Tra Ly, section from K25+600 to K26+785, Thai Binh city.
The above two projects belong to Package No. 10, a component project to strengthen the dike system in Thai Binh province in the period of 2021-2025. The construction period is 30 months, starting from December 2022.
Up to now, after more than 8 months of construction, the volume of work done at both projects has reached about 90%. Specifically, the construction unit has completed the dike cross-section with a width of 7m, a hardened width of 6m; paved the asphalt concrete road surface with a thickness of 7cm, the upper layer of crushed stone aggregate is 15cm thick, the lower layer of crushed stone aggregate is 20cm thick; reinforced the curbs on both sides of the road with filled soil, the reinforced curb width is 0.5m...
The construction unit is urgently completing the remaining items such as: leveling and reinforcing the slope up and down the dike, and filling the dike shoulder. Both projects are expected to be completed in August 2023.
Nguyen Thoi