Signing BOT contract to select highway investor in December
The document signed by the Director of the Traffic Construction Investment Project Management Board requested the Hanoi People's Committee to direct units to speed up site clearance and relocation of underground and above-ground works. In particular, localities need to promptly hand over the site at locations where weak ground must be treated in August 2024.
Ring Road 4 section through Me Linh district. Photo: Ta Hai.
Accordingly, Component Project 1.1: Compensation, support, and resettlement (including expressway system, parallel roads (urban roads), technical infrastructure, and national railway reserve corridor) in Hanoi has a total investment of about 13,362 billion VND.
In the last 4 months of 2024, the units will basically complete the items, finish the power outage, and connect the remaining points.
At the Component Project 2.1 of parallel road construction (urban road) in the Hanoi area, the contractor is focusing on speeding up construction work, gathering sand, soil, crushed stone to the construction site and loading at qualified locations. The project's construction output to date has reached 1,261/4,205 billion VND (30%).
In the last 4 months of the year, the Board will prioritize weak soil treatment locations, strive to complete the embankment and loading of locations that have been handed over before August 30; direct contractors to embank K98 soil, grade crushed stone, and speed up bridge construction.
The parallel road through Hoai Duc district is being actively deployed by the contractor to speed up progress.
At Component 3 Project on Investment in the construction of the expressway system under the public-private partnership (PPP) method, the Project Management Board is currently coordinating with relevant agencies to complete the bidding documents to select investors, and is expected to issue bidding documents in August 2024.
In case there are qualified investors participating in the bidding, by October 2024, the technical assessment, commercial financial assessment, appraisal, and approval of the investor selection results will be completed; in November 2024, the investor will establish a project enterprise and in December 2024, negotiate and sign the BOT contract.
Speed up site clearance progress, soon move technical infrastructure works
The contractor is constructing crushed stone on the construction site of Ring Road 4 - Capital Region.
In order to ensure the progress of the national key transport project Ring Road 4 - Hanoi Capital Region, at Component Project 1.1, the Project Management Board requested the Hanoi People's Committee to direct the People's Committees of Ha Dong District, Hoai Duc District, and Thuong Tin District to urgently complete the additional land acquisition work for the remaining 21/36 high-voltage pole foundations before August 30, 2024.
People's Committees of districts and towns will carry out the relocation of underground and above-ground technical infrastructure works, to be completed in the fourth quarter of 2024.
The National Power System Dispatch Center and the Northern Power System Dispatch Center support the registration of power outage plans to connect 110kV, 220kV, and 500kV lines according to the registration schedule to ensure completion of the relocation work in the first quarter of 2025.
In Component Project 2.1, Ha Dong and Thanh Oai districts need to hand over the land for the area requiring weak soil treatment before August 30, 2024 to ensure completion of the parallel road in the fourth quarter of 2025.
Five districts including Ha Dong, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai must complete site clearance before September 30, 2024; complete relocation of underground and above-ground technical infrastructure works before October 31, 2024.
At Component Project 3, the Project Management Board also requested the Department of Planning and Investment to study and assign the focal agencies of the projects to review, harmonize, balance and agree to increase or decrease the total investment between the component projects (not exceeding the total investment of the entire project) in Resolution No. 140 of the National Assembly on the implementation of Resolution No. 43, advise the City People's Committee to report to the Government as a basis for implementation...
Source: https://www.baogiaothong.vn/tien-do-moi-nhat-du-an-vanh-dai-4-vung-thu-do-192240816172558818.htm