In Hai Duong, the main route of more than 5 km has been basically completed. The contractor is constructing the traffic safety system, painting road markings, planting trees, flowers, etc.
However, the intersection area of the road leading to Highway 37 still has land issues of 3 households. One family has not agreed to the compensation and support plan, 2 families are waiting for the land acquisition boundary adjustment. The People's Committee of Chi Linh City strives to complete the payment and hand over the land to organize construction by December 2024.
Previously, to serve the construction of the access road, Hai Duong province paid more than 114.6 billion VND for site clearance for 366/369 households and individuals.
In Bac Giang, on November 13, speaking with Hai Duong Newspaper reporter, Mr. Tran Ngoc Tu, Executive Director of the Dong Viet Bridge and Bac Giang Access Road Joint Venture Project, said that the construction unit has completed all the work of paving the Dong Viet Bridge surface.
Currently, the consortium of contractors is focusing on constructing items related to the traffic safety system including line painting, anti-glare system, expansion joints, lighting... on the bridge.
Of the total 7 km of access road in Bac Giang, the construction unit has paved asphalt concrete for nearly 4 km, some sections have been paved with base stone, and the construction has been completed by excavation and unloading to treat weak soil. However, there are still 500 m of access road that are stuck with the land of residents that have not been cleared, so construction has not been possible. The scope of the Dong Phuc commune six-way intersection is still stuck with the land of nearly 50 households and organizations. Although these households have been propagandized and mobilized, they have not received money and handed over the land.
Currently, at the construction site of Dong Viet bridge and Bac Giang approach road, there are about 60 workers constructing the bridge and approach road.
According to Mr. Tu, the construction progress of the Bac Giang access road depends on the progress of site clearance. When the site is cleared, the contractor will focus on human resources and machinery to speed up the construction progress, striving to complete the cleared road section by December 31.
The Dong Viet Bridge and the approach road were started in June 2022 with a total length of more than 811 m and a bridge surface width of 23.5 m. This is the first and largest cable-stayed bridge in Bac Giang province, crossing the Thuong River, connecting Bac Giang and Hai Duong provinces. The project is invested by the Bac Giang Provincial Project Management Board for Investment and Construction of Transport and Agricultural Works.