Rach Mop sluice gate - one of the major items of the Southern Hau River water control project has completed the main items and is temporarily put into operation, contributing to responding to the drought and salinity that is forecast to become more complicated in the coming time.
On February 17, the Irrigation Construction and Investment Management Board 10 (Ministry of Agriculture and Rural Development) coordinated with the People's Committee of Soc Trang province to temporarily operate the Rach Mop sluice gate project.
Leaders of the Ministry of Agriculture and Rural Development and leaders of the People's Committee of Soc Trang province inspected the Rach Mop sluice gate project. Photo: HX
Here, the Irrigation Investment and Construction Management Board 10 said that the Rach Mop sluice gate project has completed the main items such as sluice gates and boat lock gates, ensuring the ability to control salinity in the coming time.
To ensure the official and safe operation of Rach Mop sluice gate, the Irrigation Investment and Construction Management Board 10 has been training technical staff to operate the project.
Rach Mop sluice gate construction started in January 2023, in Nhon My commune, Ke Sach district and Song Phung commune, Long Phu district, Soc Trang province.
Mr. Tran Van Lau - Chairman of Soc Trang Provincial People's Committee presented gifts to workers building Rach Mop culvert. Photo: Huynh Xay
The culvert was built on Rach Mop River with a total cost of about 500 billion VND. Accordingly, the culvert has a water clearance width of 85m with 2 culvert compartments (each compartment is 35m wide), 1 boat lock compartment is 15m wide. In addition, there are also auxiliary works such as a management house with reinforced concrete foundation and columns, automatic monitoring and surveillance system.
Mr. Tran Van Lau - Chairman of Soc Trang Provincial People's Committee said that the completion of Rach Mop sluice gate project will help control salinity, retain fresh water, creating stable and sustainable production conditions for the natural area of 19,220 hectares in Ke Sach, Chau Thanh, Long Phu districts, Soc Trang city.
At the same time, the project also helps to minimize the impact caused by drought and salinity and create a source of fresh water supply to cope with high salinity periods on the Hau River for a natural area of 36,710 hectares in Ke Sach and Chau Thanh districts (Soc Trang province) and Chau Thanh district, Nga Bay town (Hau Giang province), increasing the ability to circulate water flow, improving the efficiency of acid drainage, alum washing and drainage, and improving the environment of the project area.
Rach Mop culvert when completed. Photo: HX
In addition to Rach Mop sluice gate, Soc Trang also has Muong Khai 2 sluice gate, Tra Ech sluice gate, Cai Trung sluice gate, Cau Truong sluice gate, Tra Quyt sluice gate which need investment attention to ensure water source for production, daily life, livelihood and health of people in the coming time.
In addition to the above 5 sluices, the leaders of Soc Trang province also proposed that the Ministry of Agriculture and Rural Development support capital to build embankments for Rach Mop sluice and Phung An canal to prevent landslides, and soon deploy Bai Xao sluice and Dai Ngai sluice to store fresh water for the province.
Deputy Minister of Agriculture and Rural Development Nguyen Hoang Hiep acknowledged and highly appreciated the efforts of the locality and construction units in completing the Rach Mop sluice gate project ahead of schedule. "This is a meaningful project, together with the remaining sluice gates, ensuring production and clean water for the daily life of more than 30,000 households," said Mr. Hiep.
Leaders of the Ministry of Agriculture and Rural Development and leaders of the People's Committee of Soc Trang province worked on the Rach Mop sluice gate project and related works. Photo: HX
According to Mr. Hiep, the forecast of drought and salinity in 2025 is expected to be lower than the average of many years, with the salinity intrusion range of about 5-7km, not too severe. However, in addition to non-structural solutions, localities need to adjust the crop season and change the structure of crops and livestock accordingly.
Regarding the remaining sewer projects mentioned above, Mr. Hiep informed that the Ministry of Agriculture and Rural Development has allocated capital for implementation. The locality needs to speed up the site clearance and handover to the investor by the end of June 2025 at the latest so that construction can start simultaneously in the third quarter of 2025, ensuring the completion of the entire project by 2026.
Source: https://danviet.vn/cong-trinh-cong-quy-mo-500-ty-dong-vua-hoan-thanh-nong-dan-soc-trang-bot-lo-han-man-trong-mua-kho-2025-20250217151752869.htm