The Ministry of Transport has just issued the conclusion of a meeting to review the progress of the investment project to build the new Phong Chau bridge - Km18+300 QL32C, Phu Tho province according to the emergency construction order.

The Ministry of Transport requires the investor (Thang Long Project Management Board, Ministry of Transport) and relevant entities participating in the project to strive to perform assigned tasks within their authority with the highest sense of responsibility, to resolve any problems, and to speed up the implementation process.

w cau pc1 1318 6545.jpg
Ministry of Transport speeds up construction of new Phong Chau bridge. Photo: Duc Hoang

In particular, construction must ensure quality and progress as required, avoid waste and negativity; and strictly ensure legal procedures applicable to cases implemented under the Emergency Order.

Regarding the bridge design location, the selected plan must ensure compliance with the approved planning, with the new bridge running in the same direction as the old bridge to minimize site clearance...

Regarding the scale of bridge construction, the design must ensure compliance with approved planning, and the bridge width must be suitable for the scale of 4 motor vehicle lanes.

The Ministry of Transport requires the Thang Long Project Management Board, as the investor, to focus on implementing the development of a detailed plan to implement the project according to the Emergency Order with a completion schedule of 2025.

Also related to this project, Permanent Deputy Prime Minister Nguyen Hoa Binh signed a decision to add 800 billion VND from the central budget reserve in 2024 for the Ministry of Transport to implement the investment project to build the new Phong Chau bridge.