On March 6, General Phan Van Giang, Minister of National Defense, inspected and requested to shorten the construction progress of the new Phong Chau bridge - connecting Tam Nong and Lam Thao districts (Phu Tho province).
At the scene, Minister Phan Van Giang highly appreciated the investor, contractor, supervision consultant and the coordination of Phu Tho province in implementing the new Phong Chau bridge construction project.
The Minister emphasized that Phong Chau Bridge is an emergency construction project, of special importance to overcome damage caused by storms and floods, connect the transport network, contribute to socio-economic development, and ensure national defense and security in the region.
The inspection delegation led by General Phan Van Giang, Minister of National Defense, inspected the construction progress of the new Phong Chau bridge - connecting Tam Nong and Lam Thao districts (Photo: Phu Tho Newspaper).
The Minister requested the 12th Army Corps to increase its forces, vehicles, machinery, and modern equipment to ensure the best quality of construction; increase shifts, speed up construction progress, and soon put the project into operation to serve the people's travel needs.
Minister Phan Van Giang also requested the Project Management Board and contractors to comply with State regulations on project management; control the quality of design documents in accordance with regulations; inspect and control construction materials and supplies to ensure quality according to design requirements.
In particular, the units have increased inspection and supervision of the site, urged contractors and consultants to speed up the implementation of signed packages, determined to complete the new Phong Chau bridge in early October 2025, finishing 2 months ahead of schedule, serving the travel needs of the people and welcoming the Congress of the Party Committee of the Army.
According to design, the new Phong Chau bridge has a total length of over 652m, of which the length of the bridge to the end of the abutment is about 383m.
The starting point of the project is on National Highway 32C, in Phung Nguyen Commune, Lam Thao District; the end point is in Van Xuan Commune, Tam Nong District. The bridge is 20.5m wide, ensuring 4 lanes for motor vehicles.
The bridge is constructed using reinforced concrete beams and prestressed reinforced concrete. The main bridge consists of 3 continuous, balanced cantilever beam spans; reinforced concrete abutments and piers, and bored pile foundations.
The road connecting the two ends of the bridge ensures the scale of a level III plain road, with a design speed of 80km/h. The total investment is over 635 billion VND.
After more than 2 months, the construction unit has completed 79 bored piles for the new Phong Chau bridge, 10 days ahead of schedule as committed. Taking advantage of favorable weather, the unit is pouring concrete to cover the bottom of the pier, driving piles on the dike, digging the foundation to build the foundation and the pier body, and casting the bridge girders.