On September 14, Road Management Area III announced that Tra Khuc 2 Bridge, spanning the Tra Khuc River on National Highway 1 through Quang Ngai City, had been repaired and officially reopened to traffic after more than 2 months of repairs.
Tra Khuc 2 Bridge was repaired and officially opened to traffic on September 15.
Accordingly, after completing the repair process and conducting a load test, Road Management Area III approved the contractor's request and the supervision consultant to open the road to traffic.
The repair of Tra Khuc 2 bridge is taking place safely, the project ensures quality according to approved design documents, the bridge load test has been completed and ensures safe and smooth traffic.
Therefore, Road Management Area III approved to allow all types of vehicles to circulate through Tra Khuc 2 Bridge normally from 5:00 a.m. on September 15.
Road Management Area III requests Hoa Hoang Construction Investment and Commercial Services Limited Company (the contractor) to coordinate with relevant units to dismantle the installed road sign system (to serve traffic flow organization) so that vehicles can circulate normally.
Source: https://www.baogiaothong.vn/thong-xe-qua-cau-tra-khuc-2-tren-ql1-qua-quang-ngai-192240914170401129.htm
Comment (0)