The Government Office has just issued Notice No. 545/TB-VPCP dated December 4, 2024, concluding the Prime Minister Pham Minh Chinh's conclusion at the meeting on the progress of the Long Thanh International Airport construction investment project, connecting infrastructure and planning, urban development of Long Thanh airport and surrounding areas.
The conclusion announcement stated that the Long Thanh International Airport construction investment project is a national key project, which has been closely directed by the leaders of the Party, State and Government. Previously, the Prime Minister had directly visited the construction site 4 times to inspect and supervise, and issued many directive documents. Although the project has started very slowly compared to the required schedule, up to now, the project has achieved a lot of progress in terms of construction progress and quality as well as labor safety, including: Air traffic control tower of Component Project 2; Passenger Terminal and Runway of Component Project 3. These positive results need to be continued.
The Prime Minister acknowledged the above positive results and highly appreciated the efforts of Vietnam Airports Corporation (ACV), Vietnam Air Traffic Management Corporation (VATM), contractors, construction units, consulting units and more than 6,000 engineers, workers, and laborers who mobilized over 2,000 pieces of equipment to construct "overcoming the sun, overcoming the rain, not losing to storms and winds" , "working in 3 shifts, 4 shifts" , "through holidays, through Tet, through days off" , "eating quickly, sleeping urgently" ; contributing to speeding up construction progress, bringing projects to completion ahead of schedule.
In addition to the above achievements, the implementation of the Project still has many shortcomings, obstacles and delays in implementation, requiring each agency, entity, relevant unit and individual to seriously grasp and clearly understand their roles and responsibilities, proactively and actively perform assigned tasks, handle difficulties and obstacles in accordance with regulations and authority, promptly report to superiors when there are obstacles and problems arising beyond their authority to be determined to work together to complete the Project before December 31, 2025.
Urgently find suitable and effective solutions to speed up the progress of component projects.
The Prime Minister requested that for some works that are being implemented very slowly and do not meet requirements, there must be immediate appropriate and effective solutions to overcome and speed up progress:
Regarding Component Project 4 , the Prime Minister requested the Minister of Transport to direct relevant agencies and units to adjust the Project implementation plan in accordance with regulations and practical requirements, noting that it is necessary to clarify the work, agencies, units, and implementers, products, and completion deadline of December 31, 2025; clarify the responsibilities of organizations and individuals related to the delay, and strictly handle them according to regulations; report to the Prime Minister on the results of the assignment of implementation and review before December 15, 2024.
Regarding the Ho Chi Minh City - Long Thanh Expressway expansion project : The main reason for the delay is related to the difficulties and obstacles of the Vietnam Expressway Corporation (VEC). The Prime Minister assigned Deputy Prime Minister Ho Duc Phoc to directly direct and handle the matter thoroughly before December 10, 2024 (noting that, to meet the progress requirements, the increase in VEC's charter capital needs to take into account many options, including the option of increasing capital according to a multi-step roadmap suitable to actual requirements, the ability to receive management, the financial participation plan of the State Capital Investment Corporation SCIC...); direct the review and handling of responsibilities for organizations and individuals with delayed implementation, and report to the Prime Minister on the implementation results.
Regarding site clearance : Dong Nai Provincial People's Committee needs to focus on thoroughly handling existing problems, completing all site clearance work related to the airport, and the highway serving airport exploitation must be completed by December 2024, ensuring stable lives for households.
Regarding the second runway, the Prime Minister assigned the Minister of Transport to direct relevant units to urgently complete the processes, procedures and documents according to regulations in December 2024 so that construction can begin on January 1, 2025, without delay.
Research on the shortest route for connecting by subway
Regarding some projects and constructions connected to Long Thanh Airport:
Regarding the traffic route connecting Tan Son Nhat airport with Long Thanh airport , the Prime Minister assigned the Minister of Transport to urgently study the traffic connection plan by railway or subway in the shortest, fastest and most effective direction, and report to the Prime Minister in the first quarter of 2025.
Regarding the Ho Chi Minh City beltway and An Phu intersection projects : Ho Chi Minh City People's Committee, Dong Nai province, and VEC are responsible for quickly and urgently implementing and completing the routes, ensuring progress and quality for synchronous exploitation with the Long Thanh International Airport project immediately after being put into use.
The People's Committee of Ba Ria - Vung Tau province proactively and urgently completes traffic projects connecting to Long Thanh airport; researches to deploy traffic routes connecting directly from Ho Tram to Long Thanh airport or the fastest and shortest option to develop the Ho Tram area more effectively.
The Prime Minister requested that Project Management Boards learn from practical experience, urgently reorganize construction at the construction site, perform construction smoothly and simultaneously at many locations according to the "rolling" principle; rebuild and complete the progress critical path (gantt); urge and mobilize the total force of the main contractor and subcontractors, deploy 24/7 the work performed by modern machinery and equipment; mobilize youth, army, police... to do public service work for manual work (assigning Ministers, Heads of defense agencies, police, Ho Chi Minh Communist Youth Union...); urgently take stronger and more drastic action but must ensure labor safety at the construction site.