Faced with the urgent requirement to concentrate efforts and strive to meet the schedule committed to the Government by Vietnam Electricity Group to complete the 500kV Circuit 3 Project from Quang Trach (Quang Binh) - Pho Noi (Hung Yen) on June 30, 2024, hundreds of officers and employees of the shock team - the elite force of the Power Corporations have been and are preparing to leave for the Project.
Joining forces with Vietnam Electricity Group (EVN), Chairman of the Board of Members of the Northern Power Corporation Do Nguyet Anh said: The Corporation has sent 28 shock teams with 303 people from 27 Power Companies and Northern Power Services Company to support the construction at the 500kV circuit 3 construction site. Many shock teams have set off since May 30 to ensure that 100% of EVNNPC's support personnel are present at the construction site and will start work from June 1, 2024.
Chairman of the Board of Members of Northern Power Corporation Do Nguyet Anh
Construction and operation of the 500kV Line 3, Quang Trach - Pho Noi, with 4 routes: Pho Noi - Nam Dinh; Nam Dinh - Thanh Hoa; Thanh Hoa - Quynh Luu; Quynh Luu - Quang Trach is an important political task of the country, a great responsibility assigned to EVN by the Government. To ensure the timely completion of the committed project, Vietnam Electricity Group needs to mobilize human resources from 5 Power Corporations. "Therefore, the establishment of 28 Shock Teams of the Northern Power Corporation has been carried out urgently and quickly", the Chairman of the Board of Members of EVNNPC informed.
The members of the selected Shock Teams are qualified, voluntary staff who are ready to "brave the sun and rain", working in the spirit of "3 shifts, 4 teams" to contribute a small part to completing the project on schedule. These are also typical electricians, representing EVNNPC staff participating in the country's key energy project, expected to coordinate well with units and contractors, and carry out tasks well in the most stressful final stage of the Project.
To ensure the safety of people when the Shock Teams participate in the 500kV circuit 3 construction site, the EVNNPC Board of Directors has assigned the Deputy General Director of the Corporation - Mr. Vu Anh Phuong to directly command the force, requiring the Directors of the Power Companies to closely direct to ensure absolute safety in the movement, comply with the unified command as well as the safety procedures and regulations in performing the task. The Companies must also purchase insurance for workers working in the area.
The shock team of Son La Power Company (Northern Power Corporation) joined forces to construct the 500kV line circuit 3.
In the context of hot weather forecast or unpredictable adverse developments, it is necessary to ensure the health of workers. For the 8 provinces where the power lines pass through, the provincial power companies including: Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen, always uphold the spirit of mutual support for other units, joining hands to participate in construction on the lines.
The Northern Power Corporation determined that the task of participating in the Shock Teams to support the construction of the 500kV Line 3 Quang Trach - Pho Noi project is very important and must be carried out in an urgent time, so it is necessary to have the attention and direction, create material and spiritual conditions, provide protective equipment, materials and equipment from the unit and share from the leaders, the Boards of the Corporation, the Leaders of the Power Companies, the Trade Union organizations, and unanimously focus on the project so that workers can confidently carry out the support tasks in the Shock Team.
Sending her trust to the orange soldiers when carrying out this special mission, Ms. Do Nguyet Anh, Chairwoman of the Board of Members of EVNNPC, believes that all of the more than 300 employees participating in the shock teams of the Northern Power Corporation will always be healthy, lucky, and work side by side, striving to overcome all circumstances and harsh weather, joining hands with the National Power Transmission Corporation and Vietnam Electricity Group to successfully complete the mission, contributing to the 500kV circuit 3 project from Quang Trach - Pho Noi to be able to energize on June 30, 2024.
Progress of the 500kV line 3 project from Quang Trach to Pho Noi as of May 29, 2024:
- Completed handover of 100% of foundation positions and 489/503 anchor spaces.
- Construction work: Completed casting foundations at 1,174/1,177 positions, under construction at the remaining 3 foundation positions; completed erecting 465/1,177 steel columns; under construction at 238/1,177 steel columns; completed pulling wires at 13/503 anchorage spaces.
According to EVN
Source: https://phunuvietnam.vn/hon-300-can-bo-nhan-vien-dien-luc-mien-bac-gop-suc-thi-cong-duong-day-500kv-mach-3-20240530223828343.htm